Apenas a etapa informada é destacada. Os números e datas distinguem planos de resultados demonstrados.
Epoch’s current campus estimate: 237 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 237 MW”
Physical-stage observation dated 2026-05-04. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Building 5 steel framing is underway.”
Epoch’s dated 2026-05-04 assessment: Building 5 steel framing is underway. Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Building 5 steel framing is underway.”
Epoch estimates AI hardware: Google TPU v4, Google TPU v5e, and Google TPU v5p chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Google TPU v4, Google TPU v5e, and Google TPU v5p chips.”
Epoch dated observation: Land clearing begins for Building 1 of expansion.
“Land clearing begins for Building 1 of expansion.”
Epoch dated observation: Building 4 shell mostly complete, Building 5 steel framing is underway.
“Building 4 shell mostly complete, Building 5 steel framing is underway.”
Fotos de leitores, separadas das mídias com fontes do pin. Avalie o que você comeu ou viu e, em um pin de restaurante, marque os pratos direto na sua foto.
A primeira entrada é sempre a fonte do pin. A confiança geral é uma média ponderada de quanto cada referência sustenta os horários de início e fim usados acima; uma referência conta metade a cada 180 dias a mais em relação à mais recente.
A data salva é um rastreamento estimado ou marcador de trajetória de capacidade, não um dia de abertura exato verificado. O estado de construção segue o escopo físico datado citado; nenhuma conclusão é inferida a partir de metas decorridas.
Construction research 2026-10-24: Epoch’s[1] 2026-05-04 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Building 5 steel framing is underway.” Dated observation 2026-05-04; future trajectory rows and modeled costs are distinguished from this physical milestone.
Falta algo ou há um erro? Diga com suas palavras: um link que sustente este pin, uma data de início ou fim diferente e por quê, ou um fato que falta ou está errado. A IA confere isso com as fontes do pin, procura outras melhores e adiciona qualquer página que dê razão a você. As fontes do próprio pin continuam contando mais. Uma imagem que mostra outra coisa, ou mostra mal, também é analisada e rebaixada ou substituída.
Título original: Google Papillion AI Data Center Buildout
A observação da Epoch de 04/05/2026 documenta a construção/instalação física restante para este edifício nomeado. Em andamento não conclui edifícios operacionais anteriores ou capacidade futura. As contagens de potência e acelerador permanecem estimativas da Epoch, e não uma classificação certificada pelo operador. Os custos de capital modelados em dólares de 2025 incluem hardware de computação e não são um orçamento de construção nativo da fonte.
Campus de inferência e treinamento de IA de fronteira em hiperescala rastreado pela Epoch AI com pegadas de satélite anotadas (15 partes físicas).