| Date | Observed status |
|---|---|
| 2023-10-31 | Start of construction for the first building, according to [Applied Digital](https://ir.applieddigital.com/news-events/press-releases/detail/75/applied-digital-announces-groundbreaking-of). CoreWeave |
| 2025-05-28 | CoreWeave signed the first lease package for 250 MW. No buildings online yet. This is according to an [SEC 8-k filing](https://www.sec.gov/Archives/edgar/data/1144879/000164117225013199/form8-k.htm) f |
| 2025-08-29 | [A new 150 MW lease](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with) brings CoreWeave to 400 MW total contracted. The project |
| 2025-10-27 | The first 50 MW slice of Building 1 has reached Ready for Service status according to [this report](https://ir.applieddigital.com/news-events/press-releases/detail/133/applied-digital-achieves-ready-f |
| 2025-11-24 | [This Applied Digital report](https://ir.applieddigital.com/news-events/press-releases/detail/137/applied-digital-completes-phase-ii-ready-for-service-at) says the rest of Building 1 has reached Ready |
| 2026-03-27 | According to satellite imagery, Building 1 looks complete and in service, with the surrounding power/cooling equipment also operational. (Note: this image doesn't provide a view of buildings 2 or 3, t |
| 2026-06-30 | According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and |
| 2026-12-31 | According to the [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 2 should be online sometime in the seco |
| 2027-06-01 | According to [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 3 should come online in the first half of 2 |
Epoch AI satellite-imagery notes, in date order. · fonte
Em construção
Digital infrastructure: AI data-center campus buildout · Verificado em 2026-10-30
Apenas a etapa informada é destacada. Os números e datas distinguem planos de resultados demonstrados.
Epoch’s current campus estimate: 68 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 68 MW”
Physical-stage observation dated 2026-06-30. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Building 3 construction is well underway”
Epoch’s dated 2026-06-30 assessment: Building 3 construction is well underway Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Building 3 construction is well underway”
Epoch estimates AI hardware: Nvidia B200 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Nvidia B200 chips.”
Epoch dated observation: CoreWeave was not leased yet at this site, but this is the…
“CoreWeave was not leased yet at this site, but this is the construction start date we're using for relevance.”
Epoch dated observation: According to satellite imagery, Building 2 is fully roofed and shell…
“According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed.”
Fotos de leitores, separadas das mídias com fontes do pin. Avalie o que você comeu ou viu e, em um pin de restaurante, marque os pratos direto na sua foto.
A primeira entrada é sempre a fonte do pin. A confiança geral é uma média ponderada de quanto cada referência sustenta os horários de início e fim usados acima; uma referência conta metade a cada 180 dias a mais em relação à mais recente.
A data salva é um rastreamento estimado ou marcador de trajetória de capacidade, não um dia de abertura exato verificado. O estado de construção segue o escopo físico datado citado; nenhuma conclusão é inferida a partir de metas decorridas.
Construction research 2026-10-24: Epoch’s[1] 2026-06-30 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Building 3 construction is well underway” Dated observation 2026-06-30; future trajectory rows and modeled costs are distinguished from this physical milestone.
Falta algo ou há um erro? Diga com suas palavras: um link que sustente este pin, uma data de início ou fim diferente e por quê, ou um fato que falta ou está errado. A IA confere isso com as fontes do pin, procura outras melhores e adiciona qualquer página que dê razão a você. As fontes do próprio pin continuam contando mais. Uma imagem que mostra outra coisa, ou mostra mal, também é analisada e rebaixada ou substituída.
Título original: CoreWeave Ellendale ND AI Data Center Buildout
A observação de 30/06/2026 da Epoch documenta a construção/instalação física restante para este edifício nomeado. Em andamento não conclui edifícios operacionais anteriores ou capacidade futura. As contagens de potência e acelerador permanecem estimativas da Epoch, e não uma classificação certificada pelo operador. Os custos de capital modelados em dólares de 2025 incluem hardware de computação e não são um orçamento de construção nativo da fonte.
Campus de inferência e treinamento de IA de fronteira em hiperescala rastreado pela Epoch AI com pegadas de satélite anotadas (8 partes físicas).