Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · источник
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · источник
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · источник
| Date | Observed status |
|---|---|
| 2023-10-31 | Start of construction for the first building, according to [Applied Digital](https://ir.applieddigital.com/news-events/press-releases/detail/75/applied-digital-announces-groundbreaking-of). CoreWeave |
| 2025-05-28 | CoreWeave signed the first lease package for 250 MW. No buildings online yet. This is according to an [SEC 8-k filing](https://www.sec.gov/Archives/edgar/data/1144879/000164117225013199/form8-k.htm) f |
| 2025-08-29 | [A new 150 MW lease](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with) brings CoreWeave to 400 MW total contracted. The project |
| 2025-10-27 | The first 50 MW slice of Building 1 has reached Ready for Service status according to [this report](https://ir.applieddigital.com/news-events/press-releases/detail/133/applied-digital-achieves-ready-f |
| 2025-11-24 | [This Applied Digital report](https://ir.applieddigital.com/news-events/press-releases/detail/137/applied-digital-completes-phase-ii-ready-for-service-at) says the rest of Building 1 has reached Ready |
| 2026-03-27 | According to satellite imagery, Building 1 looks complete and in service, with the surrounding power/cooling equipment also operational. (Note: this image doesn't provide a view of buildings 2 or 3, t |
| 2026-06-30 | According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and |
| 2026-12-31 | According to the [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 2 should be online sometime in the seco |
| 2027-06-01 | According to [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 3 should come online in the first half of 2 |
Epoch AI satellite-imagery notes, in date order. · источник
Строится
Digital infrastructure: AI data-center campus buildout · Проверено 2026-10-30
Выделен только подтверждённый этап. Показатели и даты различают планы и подтверждённые результаты.
Epoch’s current campus estimate: 68 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 68 MW”
Physical-stage observation dated 2026-06-30. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Building 3 construction is well underway”
Epoch’s dated 2026-06-30 assessment: Building 3 construction is well underway Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Building 3 construction is well underway”
Epoch estimates AI hardware: Nvidia B200 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Nvidia B200 chips.”
Epoch dated observation: CoreWeave was not leased yet at this site, but this is the…
“CoreWeave was not leased yet at this site, but this is the construction start date we're using for relevance.”
Epoch dated observation: According to satellite imagery, Building 2 is fully roofed and shell…
“According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed.”
Фото читателей, отдельно от медиа пина с источниками. Оцените то, что вы ели или видели, а в пине ресторана отметьте блюда прямо на своём фото.
Первая запись — всегда источник пина. Общая достоверность — это взвешенное среднее того, насколько каждый источник подтверждает указанные выше время начала и окончания; вес источника уменьшается вдвое за каждые 180 дней разницы с самым новым.
Сохраненная дата является ориентировочным показателем отслеживания или траектории мощности, а не проверенным точным днем открытия. Статус строительства соответствует указанному датированному физическому объему; завершение не выводится из истекших целей.
Construction research 2026-10-24: Epoch’s[1] 2026-06-30 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Building 3 construction is well underway” Dated observation 2026-06-30; future trajectory rows and modeled costs are distinguished from this physical milestone.
Чего-то не хватает или есть ошибка? Напишите своими словами: ссылку, подтверждающую этот пин, другую дату начала или окончания и почему, или факт, которого нет или который неверен. ИИ сверит это с источниками пина, поищет лучшие и добавит любую страницу, которая вас подтверждает. Собственные источники пина всё равно весят больше всего. Изображение, на котором показано что-то другое или показано плохо, тоже проверяется и опускается ниже или заменяется.
Оригинальное название: CoreWeave Ellendale ND AI Data Center Buildout
В наблюдениях Epoch от 30 июня 2026 г. документально подтверждены оставшиеся физические строительные/монтажные работы для этого названного здания. В процессе не достраиваются ранее действующие здания или будущие мощности. Показатели мощности и ускорителей остаются оценками Epoch, а не рейтингом, сертифицированным оператором. Смоделированные капитальные затраты в 2025 году включают вычислительное оборудование и не являются исходным бюджетом строительства.
Гипермасштабный кампус для обучения и вывода ИИ, отслеживаемый Epoch AI с аннотированными спутниковыми следами (8 физических частей).