Этот пин следит за новостями: он показывает то, что известно сейчас, а здесь — что изменилось и почему.
Изменено@ThePinGang
Было
IAEA’s 2024 Climate Change and Nuclear Power report identifies US$4 billion expected total cost for the Natrium demonstration project, separately from the US$2 billion DOE contribution. It describes one 345 MWe net reactor at Kemmerer. This is a dated published project estimate; it is not represented as a refreshed 2026 fixed-price budget.
IAEA’s 2024 Climate Change and Nuclear Power report identifies US$4 billion expected total cost for the Natrium demonstration project, separately from the US$2 billion DOE contribution. It describes one 345 MWe net reactor at Kemmerer. This is a dated published project estimate; it is not represented as a refreshed 2026 fixed-price budget. Natrium — Kemmerer Unit 1: 345 MW generating project rating. 345 MWe net continuous reactor output; storage-assisted peak excluded
TerraPower April 23, 2026 confirms official plant construction following the construction permit. Non-nuclear site support construction started June 2024. Reactor output is 345 MWe; storage-assisted 500 MW peak output is not additional continuous generating capacity.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Изменено@ThePinGang
Было
Было
TerraPower announced the start of construction on Kemmerer Unit 1 on April 23, 2026 after receiving the NRC construction permit. Natrium’s reactor rating is 345 MW; the storage-assisted peak output is a different metric and must not be represented as the continuous reactor capacity.
Operator project page identifies Kemmerer as under construction. EPC contracting changes and schedule implications need a later sourced revisit.
GEM August 2026 snapshot: under construction. 345 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
EIA August 2026 snapshot: approvals pending. 500 MW nameplate across 1 new/recent generating units. Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
Additional source view; compare phase coverage and rating conventions before combining figures.
Additional source view; compare phase coverage and rating conventions before combining figures.
Изменено@ThePinGang
Было
TerraPower announced the start of construction on Kemmerer Unit 1 on April 23, 2026 after receiving the NRC construction permit. Natrium’s reactor rating is 345 MW; the storage-assisted peak output is a different metric and must not be represented as the continuous reactor capacity.
Operator project page identifies Kemmerer as under construction. EPC contracting changes and schedule implications need a later sourced revisit.
GEM August 2026 snapshot: under construction. 345 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
EIA August 2026 snapshot: approvals pending. 500 MW nameplate across 1 new/recent generating units. Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
Additional source view; compare phase coverage and rating conventions before combining figures.
Изменено@ThePinGang
Было
TerraPower announced the start of construction on Kemmerer Unit 1 on April 23, 2026 after receiving the NRC construction permit. Natrium’s reactor rating is 345 MW; the storage-assisted peak output is a different metric and must not be represented as the continuous reactor capacity.
Operator project page identifies Kemmerer as under construction. EPC contracting changes and schedule implications need a later sourced revisit.
GEM August 2026 snapshot: under construction. 345 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
EIA August 2026 snapshot: approvals pending. 500 MW nameplate across 1 new/recent generating units. Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
Изменено@ThePinGang
Было
GEM August 2026 snapshot: under construction. 345 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
EIA August 2026 snapshot: approvals pending. 500 MW nameplate across 1 new/recent generating units. Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
Изменено@ThePinGang
Было
GEM August 2026 snapshot: under construction. 345 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
Изменено@ThePinGang
Было
Это фото читателей, отдельно от медиа пина с источниками.
Первая запись — всегда источник пина. Общая достоверность — это взвешенное среднее того, насколько каждый источник подтверждает указанные выше время начала и окончания; вес источника уменьшается вдвое за каждые 180 дней разницы с самым новым.
Документально подтверждённый физический рубеж или датированная отметка прогресса/отчётности. Даты конца периода отражают лишь заявленный месяц/квартал и не выдумывают точную дату ввода в эксплуатацию. Оценки источников помечены и не рассматриваются как подтверждённые будущие даты открытия.
IAEA’s 2024 Climate Change and Nuclear Power report identifies US$4 billion expected total cost for the Natrium demonstration project, separately from the US$2 billion DOE contribution. It describes one 345 MWe net reactor at Kemmerer. This is a dated published project estimate; it is not represented as a refreshed 2026 fixed-price budget. Natrium — Kemmerer Unit 1: 345 MW generating project rating. 345 MWe net continuous reactor output; storage-assisted peak excluded
Чего-то не хватает или есть ошибка? Напишите своими словами: ссылку, подтверждающую этот пин, другую дату начала или окончания и почему, или факт, которого нет или который неверен. ИИ сверит это с источниками пина, поищет лучшие и добавит любую страницу, которая вас подтверждает. Собственные источники пина всё равно весят больше всего. Изображение, на котором показано что-то другое или показано плохо, тоже проверяется и опускается ниже или заменяется.
Оригинальное название: Natrium — Kemmerer Unit 1 — under construction
В докладе МАГАТЭ 2024 года Climate Change and Nuclear Power ожидаемая общая стоимость демонстрационного проекта Natrium указана в 4 млрд USD отдельно от вклада Минэнерго США в 2 млрд USD. Описан один реактор нетто-мощностью 345 МВт (эл.) в Кеммерере. Это датированная опубликованная оценка проекта; она не представлена как обновлённый в 2026 году бюджет с фиксированной ценой.[1][2]
В докладе МАГАТЭ 2024 года Climate Change and Nuclear Power ожидаемая общая стоимость демонстрационного проекта Natrium указана в 4 млрд USD отдельно от вклада Минэнерго США в 2 млрд USD. Описан один реактор нетто-мощностью 345 МВт (эл.) в Кеммерере. Это датированная опубликованная оценка проекта; она не представлена как обновлённый в 2026 году бюджет с фиксированной ценой. Natrium — Кеммерер, энергоблок 1: проектная мощность генерации 345 МВт. Чистая непрерывная мощность реактора 345 МВт (эл.); пик с поддержкой накопителя не учитывается[2]
TerraPower 23 апреля 2026 года подтвердила официальное начало строительства станции после получения разрешения на строительство. Вспомогательное неядерное строительство на площадке началось в июне 2024 года. Мощность реактора — 345 МВт (эл.); пиковая мощность 500 МВт с поддержкой накопителя не является дополнительной непрерывной генерирующей мощностью.[1]
Сохранены только проекты с документально подтверждённым физическим строительством, пуско-наладкой или открытием в 2025–2026 годах и с опубликованными стоимостью и электрической мощностью по проекту. Стоимость указана в опубликованных рамках и валюте; ориентировочных оценок и пересчёта валют нет. МВт — это мощность, а не годовая выработка электроэнергии. Ожидаемая годовая выработка, где указана, является прогнозом. Точка на карте — заявленное местоположение станции/проекта, оно может быть приблизительным. Соответствующие инвентарные представления и исключённые предложения по расширению не являются суммируемой мощностью.
Церемония начала строительства Кеммерер, энергоблок 1, предоставленная вместе с объявлением TerraPower от 23 апреля 2026 года после выдачи NRC разрешения на строительство. Это фотография мероприятия, а не готового реактора. Авторство: TerraPower; отдельный фотограф не назван. Источник и галерея; оригинал.