Этот пин следит за новостями: он показывает то, что известно сейчас, а здесь — что изменилось и почему.
Изменено@ThePinGang
Было
2027. The current operator project page identifies construction underway and expected customer supply in 2027.
Construction is verified; the completion date remains an estimate. The timeline marker represents the published target year/month, not a confirmed opening day.
LG&E/KU’s current Mill Creek 5 page states a 645 MW nameplate rating, $902 million cost, construction underway and estimated completion in 2027. Its 2024 groundbreaking release used 640 MW; the current page is used for the primary output rating. EIA’s separate 740 MW figure is retained as inventory context, not extra generating capacity.
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Operator source page; original image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Operator source page; original image.
Изменено@ThePinGang
Изменено@ThePinGang
Было
Было
LG&E/KU’s current Mill Creek 5 page states a 645 MW nameplate rating, $902 million cost, construction underway and estimated completion in 2027. Its 2024 groundbreaking release used 640 MW; the current page is used for the primary output rating. EIA’s separate 740 MW figure is retained as inventory context, not extra generating capacity.
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Operator source page; original image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Operator source page; original image.
Изменено@ThePinGang
Было
LG&E/KU’s current Mill Creek 5 page states a 645 MW nameplate rating, $902 million cost, construction underway and estimated completion in 2027. Its 2024 groundbreaking release used 640 MW; the current page is used for the primary output rating. EIA’s separate 740 MW figure is retained as inventory context, not extra generating capacity.
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Operator source page; original image.
Изменено@ThePinGang
Было
LG&E/KU’s current Mill Creek 5 page states a 645 MW nameplate rating, $902 million cost, construction underway and estimated completion in 2027. Its 2024 groundbreaking release used 640 MW; the current page is used for the primary output rating. EIA’s separate 740 MW figure is retained as inventory context, not extra generating capacity.
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Изменено@ThePinGang
Было
Было
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels.
EIA August 2026 generator inventory, plant ID 1364: Mill Creek (KY), Jefferson County, KY. Included 1 new/recent generating units with a summed nameplate rating of 740 MW.
EIA reports operation at month/year precision. The date is the last day of the earliest reported operation month/year, an estimated display boundary, not an exact opening day. Different units may have later dates. Future dates are operator-reported plans, not guarantees.
Coordinates are the EIA-reported plant point, not a verified entrance. New units at existing plants are included; the total excludes older units and battery/pumped storage. Capacity is a power rating, not annual energy output. Status was reported in August and may have changed since.
Operator rendering of Mill Creek 5. This is an illustration of the planned unit, not a photograph of a completed plant. Credit: LG&E and KU; artist not named on source page. Source page; original operator image.
Mill Creek 5 groundbreaking ceremony, November 13, 2024, as published in the operator release. Credit: LG&E and KU; photographer not named on source page. Source page; original operator image.
Это фото читателей, отдельно от медиа пина с источниками.
Первая запись — всегда источник пина. Общая достоверность — это взвешенное среднее того, насколько каждый источник подтверждает указанные выше время начала и окончания; вес источника уменьшается вдвое за каждые 180 дней разницы с самым новым.
Опубликованный срок: 2027. Строительство подтверждено документально, но этот будущий этап завершения/ввода в эксплуатацию является оценочным. Дата — это условная отметка конца года/месяца на шкале времени, а не подтверждённый день открытия. Источник: https://lge-ku.com[2][3]/mc5
Published project-specific cost for Mill Creek 5: USD 9.02e+08. Basis: Published project-specific capital/construction estimate. Published electric generating project rating for Mill Creek 5: 645 MW. Basis: Current operator page: 645 MW nameplate.[1]
LG&E and KU broke ground on Mill Creek 5 on November 13, 2024 and describe a 640 MW natural-gas combined-cycle unit expected in 2027. EIA’s[1] August 2026 construction record independently supports ongoing work. The operator’s 640 MW project rating and EIA generator nameplate rating use different reported figures; retain both labels. November 13, 2024 groundbreaking verifies physical construction.
Чего-то не хватает или есть ошибка? Напишите своими словами: ссылку, подтверждающую этот пин, другую дату начала или окончания и почему, или факт, которого нет или который неверен. ИИ сверит это с источниками пина, поищет лучшие и добавит любую страницу, которая вас подтверждает. Собственные источники пина всё равно весят больше всего. Изображение, на котором показано что-то другое или показано плохо, тоже проверяется и опускается ниже или заменяется.
Оригинальное название: Mill Creek 5 — estimated target 2027
2027. Актуальная страница проекта оператора сообщает, что строительство ведётся, а поставки потребителям ожидаются в 2027 году.[2]
Строительство подтверждено; дата завершения остаётся оценочной. Отметка на временной шкале показывает опубликованный целевой год/месяц, а не подтверждённый день открытия.
На актуальной странице Mill Creek 5 компаний LG&E/KU указаны номинальная мощность 645 МВт, стоимость 902 млн долларов, ведущееся строительство и ориентировочное завершение в 2027 году. В релизе о закладке 2024 года фигурировало 640 МВт; для основной мощности используется актуальная страница. Отдельный показатель EIA в 740 МВт сохранён как справочные данные об инвентаре, а не как дополнительная генерирующая мощность.[2][3]
Опубликованная стоимость проекта Mill Creek 5: USD 9.02e+08. Основание: Опубликованная оценка капитальных затрат/стоимости строительства проекта. Опубликованная мощность проекта электрогенерации Mill Creek 5: 645 МВт. Основание: Актуальная страница оператора: номинальная мощность 645 МВт.[2]
LG&E и KU начали строительство Mill Creek 5 13 ноября 2024 года и описывают парогазовый блок на природном газе мощностью 640 МВт, ожидаемый в 2027 году. Запись EIA о строительстве за август 2026 года независимо подтверждает продолжающиеся работы. Проектная мощность оператора 640 МВт и номинальная мощность генератора по EIA основаны на разных показателях; сохранены оба обозначения. Закладка 13 ноября 2024 года подтверждает физическое строительство.[3]
Сохранены только проекты с документально подтверждённым физическим строительством, пуско-наладкой или открытием в 2025–2026 годах и с опубликованными стоимостью и электрической мощностью по проекту. Стоимость указана в опубликованных рамках и валюте; ориентировочных оценок и пересчёта валют нет. МВт — это мощность, а не годовая выработка электроэнергии. Ожидаемая годовая выработка, где указана, является прогнозом. Точка на карте — заявленное местоположение станции/проекта, оно может быть приблизительным. Соответствующие инвентарные представления и исключённые предложения по расширению не являются суммируемой мощностью.
Визуализация оператора Mill Creek 5. Это иллюстрация планируемого блока, а не фотография построенной станции. Автор/источник: LG&E and KU; художник не указан на исходной странице. Исходная страница; оригинал изображения оператора.
Церемония закладки Mill Creek 5, 13 ноября 2024 года, опубликованная в релизе оператора. Автор/источник: LG&E and KU; фотограф не указан на исходной странице. Исходная страница; оригинал изображения оператора.
Визуализация оператора Mill Creek 5. Это иллюстрация планируемого блока, а не фотография построенной станции. Автор/источник: LG&E and KU; художник не указан на исходной странице. Исходная страница оператора; оригинал изображения.
Церемония закладки Mill Creek 5, 13 ноября 2024 года, опубликованная в релизе оператора. Автор/источник: LG&E and KU; фотограф не указан на исходной странице. Исходная страница оператора; оригинал изображения.
Строительная площадка Mill Creek 5 из галереи проекта LG&E и KU. Дата съёмки отдельно не указана. Автор/источник: LG&E and KU; фотограф не указан. Источник и галерея; оригинальный материал.
Строительная площадка Mill Creek 5 из галереи проекта LG&E и KU. Дата съёмки отдельно не указана. Автор/источник: LG&E and KU; фотограф не указан. Источник и галерея; оригинальный материал.