Waiawa, Oahu, Hawaii; retained rounded EIA 66066 Phase 2 reporting point, not the separate operating Waiawa Solar Power plantAES Distributed Energy
CONFIRMEDDate confidence: CONFIRMEDStated as firmHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all CONFIRMED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Confirmed August 21, 2023 construction start stated by AES. Actual COD is unverified; no exact 2026 day inferred from the updated schedule.[1]AES’s Waiawa Phase 2 page states construction began August 21, 2023 for 30 MWac solar and 240 MWh storage on up to 387 acres. Its updated project schedule targets operation in 2026; EIA plant 66066 lists September 2026 planned operation and more than 50% construction complete as of August.