Dubai's Hassyan Seawater Desalination Plant Completes All Phases
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins70% CONFIDENCEOverall confidence: 70%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidenceEstimated: the Dubai Media Office[1] says "All phases of the plant are scheduled to be completed in the first quarter of 2027"; a quarter is dated to its last day, 31 March 2027.
DEWA's AED 3.377 billion Hassyan reverse-osmosis plant, its first independent water producer project and one of the world's largest, is due to finish all phases in Q1 2027. The first phase was about 90% complete at last report.
AED 3.4B
1.00