DELAYEDDate confidence: DELAYEDThe date has movedHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all DELAYED pins17 months late68% CONFIDENCEOverall confidence: 68%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
AI Weekly[3] (19 Jul 2026): "targeting first operations by summer 2028"; DCD (12 Jan 2026): IID said "the project could go live as early as January 2027". Both predate the 9 Sep 2026 ruling, so the real date is unknown.Imperial Valley Computer Manufacturing's 330 MW, roughly 10B USD, 950,000 sq ft campus near the City of Imperial lost its county approval on 9 September 2026 when an Imperial County judge ruled CEQA review was required; the developer plans to seek a new trial and appeal.