463 Power House Road, Moncks Corner, South Carolina, USA (approximate address point)Pinopolis Reliability Project LLC / Aypa Power
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Filed contractual COD December 1, 2027; mechanical completion August 30, 2027 is separate. Target remains estimated.[1]Primary SCPSC filings establish Aypa’s 300 MW / 1,200 MWh four-hour LFP battery at Jefferies, with contractual commercial operation December 1, 2027. The January 2026 order exempts this project from the specific siting certificate; February withdrawal of that certificate application does not establish project cancellation.