ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
ERCOT[1] September 2026 GIS row 1538 projected COD; no commissioning approval established.ERCOT’s September 2026 report lists Spectra Solar (28INR0486), SE DC Devco, at 1,200 MW in Scurry County, with an interconnection agreement and projected November 16, 2028 COD. The earlier $1.1B budget is unsupported.
1.00