ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Enlight/Clēnera release, 10 Nov 2025: Snowflake A is "expected to reach COD during H2 2027"; Cleanview[3] lists August 2027. 1 July 2027 is the start of the stated half-year.Clēnera (Enlight) closed US$1.438 billion of construction debt in November 2025 for Snowflake A near Holbrook, Arizona: 600 MW of solar and 1,900 MWh of storage under a 20-year APS agreement, expected online in the second half of 2027; the total project cost has not been published.
1.00