ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
No schedule is published. The date is 1 April 2025, when Takanock filed Kenneth Davies' direct testimony in IURC Cause No. 46183 describing the project; it is not a construction date.[1]Takanock's Project Beckham is a planned data center of about 1,500 MW near Goshen in Elkhart County, Indiana; Takanock told the Indiana regulator in April 2025 that NIPSCO wanted it to pay for more than 15 miles of new 345 kV lines, and trackers now describe the project as stalled. No cost has been published.
1.00