ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
WhiteFiber's[1] own NC-1 page states a targeted go-live of December 2025 for the first 24 MW; whether it was met is unconfirmed.WhiteFiber acquired a 96-acre industrial property of roughly 1 million sq ft in Madison, NC to retrofit as a Tier 3 AI data center. It reports 99 MW secured with potential growth to 200 MW, and targeted 24 MW online in Q4 2025.