22715 Relocation Drive, Sterling, Virginia; Census-geocoded current operator IAD03 address contextAligned Data Centers
CONFIRMEDDate confidence: CONFIRMEDStated as firmHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all CONFIRMED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Confirmed July 26, 2022 announcement dateline; not COD. Exact commissioning and current capacity remain unresolved.[1]Aligned’s July 26, 2022 announcement describes a 10-acre Sterling campus master-planned for two buildings, with IAD03 phase-one delivery then targeted for fall 2023. Its current exact-building listing gives 22715 Relocation Drive, Sterling.