ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Estimated commercial operation target of February 2028 based on ERCOT[1][2] generator interconnection queue schedule and state regulatory filings.Energy Management is developing the 300M USD, 307.4 MW / 1,230 MWh utility-scale battery energy storage system in Cooke County, Texas, delivering dispatchable reserve power to the ERCOT North Zone.
$300M
1.00