Estimated: Abeja Solar Farm EIA plant 68347 reporting point, Bee County, Texas; approximate project contextAbeja Solar Farm LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
June 7, 2029 is the later ERCOT[1] projected COD; EIA[2] July 2028 conflicts. Neither date is confirmed operation.EIA plant 68347 lists Abeja Solar Farm LLC’s Bee County project at 200 MW, with July 2028 proposed operation and approvals not initiated. The later September 2026 ERCOT GIS request 27INR0372 instead reports 200.84 MW and June 7, 2029 projected COD.
1.00