Concourse D, Hartsfield-Jackson Atlanta International Airport, Atlanta, GA 30320
Hartsfield-Jackson Atlanta International Airport
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
The airport's phase-two announcement has "19 modules planned in total by the project's completion in the summer of 2029" - a season, not a fixed day.[1]Atlanta is rebuilding Concourse D in place, floating 19 prefabricated steel modules into position overnight to make the 1980s concourse about 60 percent wider and able to take larger aircraft while it keeps operating. Phase two began in January 2025 with the sixth module.
$1.4B
1.00