ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins73% CONFIDENCEOverall confidence: 73%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
DCD, 29 July 2026: "at full build-out, the campus could support up to 1.8GW of utility capacity and more than 1.2GW of compute capacity by 2032"; POWER and DOE-based reports say construction is expected to finish in 2031. No month is given.[1]Brookfield will lease land at the DOE Paducah Site in McCracken County, Kentucky for a campus of up to 1,800 MW of utility capacity (more than 1,200 MW of compute) with NextEra building up to 4.6 GW of dedicated generation and storage; the coalition cites 100B USD of private investment and full build-out in 2032.
$100B
1.00