ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins91% CONFIDENCEOverall confidence: 91%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
July 1, 2026 is an unverified legacy tracker timeline anchor, not an operator-published opening day. Stage is supported separately by the cited evidence.[1]August reporting explicitly verifies 5C constructing the USD1.3bn Prime Ohio Corporate Park facility by retrofitting and expanding the former LexisNexis center. In Progress applies to that phased build, not all capacity complete. The operator’s campus catalog distinguishes committed capacity from future delivery; the tracker’s 150MW and parcel number are not independently verified and are removed.
$1.3B
1.00