ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Start is the August 2025 planning-commission request; the project ended on its 12 Sept 2025 withdrawal and no completion target ever existed.[1]In August 2025 convenience-store owner Alpesh Patel's attorney asked Blakely Borough to rezone a residential tract for an AI data center of four buildings using about 1.5 gigawatts. After more than 100 residents objected, the developers withdrew the zoning request on 12 September 2025 and said the data center would no longer be pursued. Blakely then advanced a zoning amendment limiting future data centers to one overlay district.