5977 Silver Creek Valley Road, San José, California; Census-geocoded address context, not surveyed parcel centroid
Prologis
CONFIRMEDDate confidence: CONFIRMEDStated as firmHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all CONFIRMED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
The confirmed event is September 18, 2026 application docketing. January 2028 is the proposed construction start, not COD.[1]Prologis’s September 2026 CEC application proposes a 516,000 sqft data center on 15.13 acres at 5977 Silver Creek Valley Road. It describes 99 MW total load and 44 backup generators; the project remains under review.
1.00