ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
March 1 is a month-only placeholder interpreting brochure 3/27 as March 2027 initial move-in; it is a proposal, not confirmed commissioning. Verify the 54 MW phase label and current schedule.[1]DC BLOX’s Birmingham specification identifies a proposed 263,000 sqft, two-story BHM1-B expansion, with 40 MW critical and 60 MW gross power. Its initial move-in line reads 3/27 with 54MW; the meaning of that interim MW figure requires confirmation.
1.00