CONFIRMEDDate confidence: CONFIRMEDStated as firmHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all CONFIRMED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
June 15, 2021 is the queue GIA-completion milestone (doneDate and giaToExec), not COD. Confirmed as a dated queue record; negotiated August 2023 does not establish realized operation.MISO’s live J1072 record identifies a 150 MW solar project in Mower County at Adams 345 kV, transmission owner Northern States Power Company, GIA completed June 15, 2021 and post-GIA status Under Construction. Its August 1, 2023 negotiated in-service target is stale and does not prove operation.
1.00