ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Unverified legacy December 2028 date; current developer statement establishes permitting status, not COD.[1]Cloverleaf’s September 28, 2026 statement withdrew its initial power-generation application while keeping Bluestem’s data-center rezoning active. Its project page commits to closed-loop cooling; the prior 240 MW and $1.5B claims lack current primary support.
1.00