CONFIRMEDDate confidence: CONFIRMEDStated as firmHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all CONFIRMED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
Applied Digital[1][2] October 27, 2025 release confirms first 50 MW phase Ready for Service on that date; campus delivery is phased. October 2, 2026 release confirms 250 MW then operating.Applied Digital reported 250 MW of operational critical IT capacity at Polaris Forge 1 in Ellendale on October 2, 2026. The full contracted deployment is 400 MW; the first 50 MW phase reached service on October 27, 2025.