ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins95% CONFIDENCEOverall confidence: 95%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 75% confidence or better
June 1, 2030 remains an unverified legacy estimated anchor. Construction is conditional on final permits, then 48–60 months phased buildout; no exact schedule can be calculated from an unknown final-permit date.[1]Prometheus’s June 2026 announcement gives its 506-acre Evanston campus 1.25 GW initial capacity and a path to 5 GW. A separate August power-facility recommendation was not final approval; the prior 250 MW / $2B tracker scope is superseded.