ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins66% CONFIDENCEOverall confidence: 66%How well the pin's source and references back up its dates.Weighted average of how firmly 6 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidencein 77 days
Cleanview[4] dates phase 1 (operating) to 2025 and phase 2 (under construction) to 2027; Baxtel[3] records phase 1 topping out in June 2024; no month is published for phase 2.Aligned Data Centers is building PHX-06 in two phases (456,946 sq ft) at Price Road and Innovation Street in Chandler, Arizona; Cleanview lists 69.8 MW per phase, 139.6 MW in all, with phase 1 operating and phase 2 due in 2027, and the only published cost is a 115M USD site purchase.