ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins67% CONFIDENCEOverall confidence: 67%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidencein 76 days
Only a year is published: Cleanview[2] lists 2026 for PHX-13 and no month appears in Aligned, Lewis or DCD material; because 1 January 2026 has already passed for a building still under construction, the last day of 2026 is used. Lewis says the work is "spread across two phases".Aligned Data Centers is building PHX-13, a two-story 445,000 sq ft data center at 8805 N Reems Road in Waddell (Glendale area), Maricopa County, Arizona: 72 MW per contractor Lewis, 82.8 MW facility power in Cleanview, in APS territory; no cost has been published.