Energy: battery storage · ตรวจสอบ 2026-10-30
เน้นเฉพาะขั้นตอนที่มีรายงาน ตัวเลขและวันที่แยกแผนออกจากผลที่พิสูจน์แล้ว
200 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"Towerline","summerNetMW":200.0”
2027-01-31; requested date only, not an achieved opening.
“"projectNumber":"J3298","queueDate":"2024-04-17T04:00:00+00:00","inService":"2027-01-31T05:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":""”
Battery Storage; Towerline.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J3298","queueDate":"2024-04-17T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J3298","queueDate":"2024-04-17T04:00:00+00:00","inService":"2027-01-31T05:00:00+00:00"”
หมุดนี้ติดตามข่าว แสดงสิ่งที่รู้ ณ ตอนนี้ และที่นี่คือสิ่งที่เปลี่ยนไปและสาเหตุ
แก้ไขแล้วโดย @ThePinGang
NextEra Energy Resources development of the Towerline Clean Energy Storage Center in Tazewell County, Illinois. EncompassingJ3298 is a 200 MW / 800 MWh of utility-grade battery storage, the system interfaces with high-voltage 138 kV transmission lines near Peoria to provide rapid-response frequency stability and support regional decarbonization targets.battery storage interconnection request in Tazewell, IL. The grid operator lists its queue status as Active. The requested in-service date is 2027-01-31; this is a planning date.
NextEra Energy Resources filed zoning and transmission applications for the Towerline Clean Energy Storage Center. Provides 200 MW / 800 MWh of four-hour grid-tied battery storage in Tazewell County, Illinois. RepresentsJ3298 is a 200 MW battery storage interconnection request in Tazewell, IL. The grid operator lists its queue status as Active. The requested in-service date is 2027-01-31; this is a 210 million USD clean energy capital development near the Peoria industrial center. Interconnects to 138 kV high-voltage circuits under MISO regional queue review. Supplies rapid-response capacity firming, local transmission relief, and decarbonization support. Timeline: planned project targeting commercial operation in January 2027 (estimated) under regional grid interconnection queue and state regulatory schedules.planning date. The point of interconnection is Towerline. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
แก้ไขแล้วโดย @ThePinGang
… capacity firming, local transmission relief, and decarbonization support. Timeline: planned project targeting commercial operation in January 2027 (estimated) under regional grid interconnection queue and state regulatory schedules.
แก้ไขแล้วโดย @ThePinGang
ภาพจากผู้อ่าน แยกจากสื่อที่มีแหล่งอ้างอิงของพิน ให้คะแนนสิ่งที่คุณกินหรือเห็น และในพินร้านอาหารให้แท็กเมนูบนภาพของคุณได้เลย
รายการแรกคือแหล่งที่มาของหมุดเสมอ ความเชื่อมั่นโดยรวมคือค่าเฉลี่ยถ่วงน้ำหนักว่าแต่ละแหล่งอ้างอิงสนับสนุนเวลาเริ่มและสิ้นสุดด้านบนมากเพียงใด แหล่งอ้างอิงจะมีน้ำหนักลดลงครึ่งหนึ่งทุก ๆ 180 วันที่เก่ากว่าแหล่งล่าสุด
มีอะไรขาดหรือผิดไหม บอกด้วยคำพูดของคุณเอง: ลิงก์ที่สนับสนุนหมุดนี้ วันที่เริ่มหรือสิ้นสุดที่ต่างออกไปพร้อมเหตุผล หรือข้อเท็จจริงที่ขาดหรือผิด AI จะตรวจสอบกับแหล่งที่มาของหมุด ค้นหาแหล่งที่ดีกว่า และเพิ่มหน้าที่สนับสนุนคุณ แหล่งที่มาของหมุดเองยังคงมีน้ำหนักมากที่สุด รูปภาพที่แสดงสิ่งอื่นหรือแสดงได้ไม่ดีก็จะถูกตรวจสอบ และเลื่อนลงหรือแทนที่
ชื่อต้นฉบับ: Towerline: 200 MW Battery Interconnection Request J3298
Power storage200 MW · J3298: 200 MW requested battery storage. Queue status: Active. Requested date: 2027-01-31. Not current measured generation; No annual energy or battery MWh inferred. · source