Energy: battery storage · ตรวจสอบ 2026-10-30
เน้นเฉพาะขั้นตอนที่มีรายงาน ตัวเลขและวันที่แยกแผนออกจากผลที่พิสูจน์แล้ว
250 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"Batesville 138kV Substation","summerNetMW":250.0”
2027-09-30; requested date only, not an achieved opening.
“"projectNumber":"J2581","queueDate":"2022-09-15T04:00:00+00:00","inService":"2027-09-30T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":"Not Started"”
Battery Storage; Batesville 138kV Substation.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J2581","queueDate":"2022-09-15T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J2581","queueDate":"2022-09-15T04:00:00+00:00","inService":"2027-09-30T04:00:00+00:00"”
หมุดนี้ติดตามข่าว แสดงสิ่งที่รู้ ณ ตอนนี้ และที่นี่คือสิ่งที่เปลี่ยนไปและสาเหตุ
แก้ไขแล้วโดย @ThePinGang
MISO regional transmission interconnection development of the Batesville Energy Storage Center in Ripley County, Indiana. SupplyingJ2581 is a 250 MW / 1,000 MWh of utility-scale battery energy storage, the facility interfaces with the Batesville 138 kV substation to provide rapid frequency response, grid inertia, and capacity firming across southeastern Indiana.battery storage interconnection request in Ripley, IN. The grid operator lists its queue status as Active. The requested in-service date is 2027-09-30; this is a planning date.
Batesville Energy Storage LLC submitted interconnection filings for the Batesville Energy Storage CenterJ2581 is a 250 MW battery storage interconnection request in Ripley County, Indiana. Deploys 250 MW / 1,000 MWh of utility-scale four-hour duration lithium-ion battery storage. Represents an estimated 250 million USD private clean energy infrastructure investment in southeastern Indiana. Interconnects to the Batesville 138 kV substation within the MISO transmission footprint. Provides essential rapid frequency regulation, system inertia, and regional capacity firming. Timeline: planned project targeting commercial operation in September 2027 (estimated) under MISO interconnection queue and state regulatory schedules.Ripley, IN. The grid operator lists its queue status as Active. The requested in-service date is 2027-09-30; this is a planning date. The point of interconnection is Batesville 138kV Substation. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
แก้ไขแล้วโดย @ThePinGang
… frequency regulation, system inertia, and regional capacity firming. Timeline: planned project targeting commercial operation in September 2027 (estimated) under MISO interconnection queue and state regulatory schedules.
แก้ไขแล้วโดย @ThePinGang
ภาพจากผู้อ่าน แยกจากสื่อที่มีแหล่งอ้างอิงของพิน ให้คะแนนสิ่งที่คุณกินหรือเห็น และในพินร้านอาหารให้แท็กเมนูบนภาพของคุณได้เลย
รายการแรกคือแหล่งที่มาของหมุดเสมอ ความเชื่อมั่นโดยรวมคือค่าเฉลี่ยถ่วงน้ำหนักว่าแต่ละแหล่งอ้างอิงสนับสนุนเวลาเริ่มและสิ้นสุดด้านบนมากเพียงใด แหล่งอ้างอิงจะมีน้ำหนักลดลงครึ่งหนึ่งทุก ๆ 180 วันที่เก่ากว่าแหล่งล่าสุด
มีอะไรขาดหรือผิดไหม บอกด้วยคำพูดของคุณเอง: ลิงก์ที่สนับสนุนหมุดนี้ วันที่เริ่มหรือสิ้นสุดที่ต่างออกไปพร้อมเหตุผล หรือข้อเท็จจริงที่ขาดหรือผิด AI จะตรวจสอบกับแหล่งที่มาของหมุด ค้นหาแหล่งที่ดีกว่า และเพิ่มหน้าที่สนับสนุนคุณ แหล่งที่มาของหมุดเองยังคงมีน้ำหนักมากที่สุด รูปภาพที่แสดงสิ่งอื่นหรือแสดงได้ไม่ดีก็จะถูกตรวจสอบ และเลื่อนลงหรือแทนที่
ชื่อต้นฉบับ: Batesville: 250 MW Battery Interconnection Request J2581
Power storage250 MW · J2581: 250 MW requested battery storage. Queue status: Active. Requested date: 2027-09-30. Not current measured generation; No annual energy or battery MWh inferred. · source