ประกาศแล้ว
Energy: photovoltaic generation · ตรวจสอบ 2026-10-30
เน้นเฉพาะขั้นตอนที่มีรายงาน ตัวเลขและวันที่แยกแผนออกจากผลที่พิสูจน์แล้ว
290 MW photovoltaic generation request; preliminary interconnection scope, not measured output.
“"poiName":"GALLAGHER - TWINING 138.0kV","summerNetMW":290.0”
2028-11-01; requested date only, not an achieved opening.
“"projectNumber":"J3274","queueDate":"2024-04-15T04:00:00+00:00","inService":"2028-11-01T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":""”
Solar; GALLAGHER - TWINING 138.0kV.
“"fuelType":"Solar","facilityType":"Photovoltaic"”
Interconnection request received
“"projectNumber":"J3274","queueDate":"2024-04-15T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J3274","queueDate":"2024-04-15T04:00:00+00:00","inService":"2028-11-01T04:00:00+00:00"”
หมุดนี้ติดตามข่าว แสดงสิ่งที่รู้ ณ ตอนนี้ และที่นี่คือสิ่งที่เปลี่ยนไปและสาเหตุ
แก้ไขแล้วโดย @ThePinGang
Consumers Energy regional transmission development of the Gallagher to Twining Clean Solar ProjectJ3274 is a 290 MW photovoltaic generation interconnection request in Ogemaw County, Michigan. Generating 290 MWac of renewable power, the facility connects to regional 138 kV transmission lines to inject clean electricity into the Michigan lower peninsula grid.Ogemaw, MI. The grid operator lists its queue status as Active. The requested in-service date is 2028-11-01; this is a planning date.
Consumers Energy filed renewable resource applications for the Gallagher to Twining Clean Solar ProjectJ3274 is a 290 MW photovoltaic generation interconnection request in Ogemaw County, Michigan. Delivers 290 MWac of clean utility solar electricity across northern lower Michigan. Represents an estimated 310 million USD clean power infrastructure development. Interconnects to regional 138 kV transmission circuits under MISO oversight. Injects emission-free power into the Michigan lower peninsula grid while generating local tax revenues. Timeline: planned project targeting commercial operation in November 2028 (estimated) under MISO interconnection queue and state regulatory schedules.Ogemaw, MI. The grid operator lists its queue status as Active. The requested in-service date is 2028-11-01; this is a planning date. The point of interconnection is GALLAGHER - TWINING 138.0kV. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
แก้ไขแล้วโดย @ThePinGang
… lower peninsula grid while generating local tax revenues. Timeline: planned project targeting commercial operation in November 2028 (estimated) under MISO interconnection queue and state regulatory schedules.
ภาพจากผู้อ่าน แยกจากสื่อที่มีแหล่งอ้างอิงของพิน ให้คะแนนสิ่งที่คุณกินหรือเห็น และในพินร้านอาหารให้แท็กเมนูบนภาพของคุณได้เลย
รายการแรกคือแหล่งที่มาของหมุดเสมอ ความเชื่อมั่นโดยรวมคือค่าเฉลี่ยถ่วงน้ำหนักว่าแต่ละแหล่งอ้างอิงสนับสนุนเวลาเริ่มและสิ้นสุดด้านบนมากเพียงใด แหล่งอ้างอิงจะมีน้ำหนักลดลงครึ่งหนึ่งทุก ๆ 180 วันที่เก่ากว่าแหล่งล่าสุด
มีอะไรขาดหรือผิดไหม บอกด้วยคำพูดของคุณเอง: ลิงก์ที่สนับสนุนหมุดนี้ วันที่เริ่มหรือสิ้นสุดที่ต่างออกไปพร้อมเหตุผล หรือข้อเท็จจริงที่ขาดหรือผิด AI จะตรวจสอบกับแหล่งที่มาของหมุด ค้นหาแหล่งที่ดีกว่า และเพิ่มหน้าที่สนับสนุนคุณ แหล่งที่มาของหมุดเองยังคงมีน้ำหนักมากที่สุด รูปภาพที่แสดงสิ่งอื่นหรือแสดงได้ไม่ดีก็จะถูกตรวจสอบ และเลื่อนลงหรือแทนที่
ชื่อต้นฉบับ: Gallagher to Twining: 290 MW Solar Interconnection Request J3274
Power generation290 MW · J3274: 290 MW requested photovoltaic generation. Queue status: Active. Requested date: 2028-11-01. Not current measured generation; No annual energy or battery MWh inferred. · source