Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · แหล่งที่มา
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · แหล่งที่มา
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · แหล่งที่มา
| Date | Observed status |
|---|---|
| 2023-10-31 | Start of construction for the first building, according to [Applied Digital](https://ir.applieddigital.com/news-events/press-releases/detail/75/applied-digital-announces-groundbreaking-of). CoreWeave |
| 2025-05-28 | CoreWeave signed the first lease package for 250 MW. No buildings online yet. This is according to an [SEC 8-k filing](https://www.sec.gov/Archives/edgar/data/1144879/000164117225013199/form8-k.htm) f |
| 2025-08-29 | [A new 150 MW lease](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with) brings CoreWeave to 400 MW total contracted. The project |
| 2025-10-27 | The first 50 MW slice of Building 1 has reached Ready for Service status according to [this report](https://ir.applieddigital.com/news-events/press-releases/detail/133/applied-digital-achieves-ready-f |
| 2025-11-24 | [This Applied Digital report](https://ir.applieddigital.com/news-events/press-releases/detail/137/applied-digital-completes-phase-ii-ready-for-service-at) says the rest of Building 1 has reached Ready |
| 2026-03-27 | According to satellite imagery, Building 1 looks complete and in service, with the surrounding power/cooling equipment also operational. (Note: this image doesn't provide a view of buildings 2 or 3, t |
| 2026-06-30 | According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and |
| 2026-12-31 | According to the [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 2 should be online sometime in the seco |
| 2027-06-01 | According to [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 3 should come online in the first half of 2 |
Epoch AI satellite-imagery notes, in date order. · แหล่งที่มา
กำลังก่อสร้าง
Digital infrastructure: AI data-center campus buildout · ตรวจสอบ 2026-10-30
เน้นเฉพาะขั้นตอนที่มีรายงาน ตัวเลขและวันที่แยกแผนออกจากผลที่พิสูจน์แล้ว
Epoch’s current campus estimate: 68 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 68 MW”
Physical-stage observation dated 2026-06-30. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Building 3 construction is well underway”
Epoch’s dated 2026-06-30 assessment: Building 3 construction is well underway Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Building 3 construction is well underway”
Epoch estimates AI hardware: Nvidia B200 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Nvidia B200 chips.”
Epoch dated observation: CoreWeave was not leased yet at this site, but this is the…
“CoreWeave was not leased yet at this site, but this is the construction start date we're using for relevance.”
Epoch dated observation: According to satellite imagery, Building 2 is fully roofed and shell…
“According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed.”
ภาพจากผู้อ่าน แยกจากสื่อที่มีแหล่งอ้างอิงของพิน ให้คะแนนสิ่งที่คุณกินหรือเห็น และในพินร้านอาหารให้แท็กเมนูบนภาพของคุณได้เลย
รายการแรกคือแหล่งที่มาของหมุดเสมอ ความเชื่อมั่นโดยรวมคือค่าเฉลี่ยถ่วงน้ำหนักว่าแต่ละแหล่งอ้างอิงสนับสนุนเวลาเริ่มและสิ้นสุดด้านบนมากเพียงใด แหล่งอ้างอิงจะมีน้ำหนักลดลงครึ่งหนึ่งทุก ๆ 180 วันที่เก่ากว่าแหล่งล่าสุด
วันที่ที่บันทึกไว้คือการติดตามโดยประมาณหรือเครื่องหมายวิถีความจุ ไม่ใช่วันเปิดทำการที่แน่นอนที่ได้รับการยืนยัน สถานะการก่อสร้างเป็นไปตามขอบเขตทางกายภาพที่ลงวันที่อ้างถึง ไม่มีการอนุมานความสำเร็จจากเป้าหมายที่ผ่านไป
Construction research 2026-10-24: Epoch’s[1] 2026-06-30 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Building 3 construction is well underway” Dated observation 2026-06-30; future trajectory rows and modeled costs are distinguished from this physical milestone.
มีอะไรขาดหรือผิดไหม บอกด้วยคำพูดของคุณเอง: ลิงก์ที่สนับสนุนหมุดนี้ วันที่เริ่มหรือสิ้นสุดที่ต่างออกไปพร้อมเหตุผล หรือข้อเท็จจริงที่ขาดหรือผิด AI จะตรวจสอบกับแหล่งที่มาของหมุด ค้นหาแหล่งที่ดีกว่า และเพิ่มหน้าที่สนับสนุนคุณ แหล่งที่มาของหมุดเองยังคงมีน้ำหนักมากที่สุด รูปภาพที่แสดงสิ่งอื่นหรือแสดงได้ไม่ดีก็จะถูกตรวจสอบ และเลื่อนลงหรือแทนที่
ชื่อต้นฉบับ: CoreWeave Ellendale ND AI Data Center Buildout
เอกสารการสังเกตการณ์ประจำปี 2026-06-30 ของ Epoch ยังคงมีการก่อสร้าง/การติดตั้งทางกายภาพสำหรับโครงสร้างที่มีชื่อนี้ In Progress ไม่ได้ก่อสร้างอาคารปฏิบัติการก่อนหน้านี้หรือกำลังการผลิตในอนาคตให้แล้วเสร็จ จำนวนกำลังและคันเร่งยังคงเป็นประมาณการของ Epoch ไม่ใช่ระดับที่ผู้ปฏิบัติงานรับรอง ต้นทุนเงินทุนตามแบบจำลองปี 2025 รวมฮาร์ดแวร์ประมวลผลแล้ว และไม่ใช่งบประมาณการก่อสร้างจากต้นทาง
วิทยาเขตการฝึกอบรม AI ระดับแนวหน้าและอนุมานระดับไฮเปอร์สเกลติดตามโดย Epoch AI พร้อมรอยเท้าดาวเทียมที่มีคำอธิบายประกอบ (8 ส่วนทางกายภาพ)