150th Street W / Acorn Trail, Faribault, Minnesota; Census-geocoded intersection context, proposed site lies south/eastArcher Datacenters
The confirmed milestone is the July 7, 2026 review extension; March 31, 2027 is a supplemental-review deadline, not opening.[1]
Faribault extended Archer’s supplemental environmental review deadline to March 31, 2027 following a June 2026 court ruling. The operator advertises 120 MW total potential power; the city describes up to 500,000 sqft on roughly 87 acres.