Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · nguồn
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · nguồn
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · nguồn
| Date | Observed status |
|---|---|
| 2024-05-30 | Land clearing begins |
| 2026-04-08 | Buildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site. We expect around 3 more months needed for commissioning and server installation. |
| 2026-08-07 | Building 1 is confirmed operational via drone imagery with 8/9 group of coolers with spinning fans. Imagery also confirms all cooling and power infrastructure in place for Building 2. |
| 2026-11-05 | Building 2 is operational assuming a 3 month lag compared to Building 1. |
Epoch AI satellite-imagery notes, in date order. · nguồn
Đang xây dựng
Data center · Kiểm tra 2026-10-31
Chỉ giai đoạn được báo cáo được đánh dấu. Số liệu và ngày tháng phân biệt kế hoạch với kết quả đã chứng minh.
$800 million
“The $800 million investment will support 100 new operational jobs.”
100 operational jobs and 1,000 construction jobs
“will bring 100 operational jobs as well as 1,000 construction jobs”
715,000 sq ft
“the 715,000-square-foot data center, located in the Sage Mill Industrial Park in Aiken County”
300+ acres
“Situated on a 300+ acre site in Aiken County, South Carolina”
69 MW now; 129 MW projected
“supported by 69 MW of IT power”
Building 1 operational; Building 2 commissioning
“Building 1 is confirmed operational via drone imagery with 8/9 group of coolers with spinning fans.”
Land clearing begins (satellite)
“Land clearing begins”
Meta announces $800 million Aiken County data center
“The $800 million investment will support 100 new operational jobs.”
SELC files FOIA request on projected water use and incentives
Meta's $800 million investment will significantly impact our economy, creating valuable jobs and further driving innovation.
It will be a significant addition to our tax base, and it demonstrates the wisdom of maintaining a low-tax, business-friendly environment.
Some people love them and some people hate them,
Transparency is essential when it comes to protecting the water South Carolinians rely on for their livelihoods, health, and recreation,
| Meta to build $800 million data center in Aiken County, creating 100 jobs · 29 thg 8, 2024 | 0.80 |
|---|---|
| Meta to establish first South Carolina operation in Aiken County · 29 thg 8, 2024 | 0.80 |
| Environmental group requests water usage information for SC Meta data center · 17 thg 3, 2025 | -0.40 |
| Discover Aiken: Data center projects bringing new opportunities · 30 thg 12, 2025 | 0.00 |
Ảnh của độc giả, tách biệt với phương tiện có nguồn của ghim. Hãy chấm điểm món bạn đã ăn hoặc thấy, và với ghim nhà hàng, gắn thẻ món ngay trên ảnh của bạn.
Mục đầu tiên luôn là nguồn của ghim. Độ tin cậy tổng thể là trung bình có trọng số về mức độ mỗi tài liệu ủng hộ thời điểm bắt đầu và kết thúc được dùng ở trên; một tài liệu được tính giảm một nửa cho mỗi 180 ngày cũ hơn tài liệu mới nhất.
Bắt đầu là quá trình giải phóng mặt bằng bằng vệ tinh của Epoch[3] (30 tháng 5 năm 2024); bản phát hành của chính phủ cho biết sẽ hoạt động vào mùa xuân năm 2027 (độ chính xác theo mùa), vì vậy endDate không có giá trị.
Cited in the project timeline.[1]
Construction research 2026-10-24: Epoch’s[1] 2026-04-08 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “there's still some equipment strewn around the site” Dated observation 2026-04-08; future trajectory rows and modeled costs are distinguished from this physical milestone.
Cited in the project timeline.[1]
Cited in the project timeline.[1]
Thiếu hay sai điều gì? Hãy nói bằng lời của bạn: một liên kết củng cố ghim này, một ngày bắt đầu hoặc kết thúc khác kèm lý do, hoặc một thông tin còn thiếu hay sai. AI đối chiếu với các nguồn của ghim này, tìm nguồn tốt hơn và thêm mọi trang ủng hộ bạn. Các nguồn của chính ghim vẫn được tính nhiều nhất. Hình ảnh thể hiện nội dung khác hoặc thể hiện kém cũng được xem xét, rồi bị hạ xuống hoặc thay thế.
Tiêu đề gốc: Meta Aiken AI Data Center Buildout
Trung tâm dữ liệu Nam Carolina đầu tiên của Meta là một khuôn viên được tối ưu hóa AI rộng 715.000 foot vuông trị giá 800 triệu USD tại Khu công nghiệp Sage Mill gần Graniteville ở Quận Aiken. Việc giải phóng mặt bằng bắt đầu vào tháng 5 năm 2024, quá trình đánh giá dựa trên máy bay không người lái của Epoch xác nhận Tòa nhà 1 đi vào hoạt động vào tháng 8 năm 2026 trong khi Tòa nhà 2 vẫn đang được đưa vào vận hành và mục tiêu đã nêu của Meta cho khuôn viên trường là mùa xuân năm 2027.
Tài liệu quan sát ngày 08-04-2026 của Epoch ghi lại việc xây dựng/lắp đặt vật lý còn lại cho công trình xây dựng được đặt tên này. Đang tiến hành không hoàn thiện các tòa nhà đang vận hành trước đó hoặc công suất trong tương lai. Số lượng công suất và máy gia tốc vẫn là ước tính của Epoch, không phải là xếp hạng được nhà điều hành chứng nhận. Chi phí vốn theo mô hình năm 2025 bao gồm phần cứng máy tính và không phải là ngân sách xây dựng nguồn gốc.
Cơ sở đào tạo và suy luận AI biên giới siêu quy mô được Epoch AI theo dõi với dấu chân vệ tinh được chú thích (6 phần vật lý).
“the Southern Environmental Law Center requested documents from Aiken County regarding the anticipated water usage of Meta's proposed data center”
Data center under construction at Sage Mill
“Meta is building one of the massive information storage facilities at the Sage Mill Industrial Park in the Graniteville/Vaucluse area.”
Buildings 1 and 2 nearly complete (satellite)
“Buildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site.”
Building 1 confirmed operational via drone imagery
“Building 1 is confirmed operational via drone imagery with 8/9 group of coolers with spinning fans.”
Building 2 operational (Epoch projection)
“Building 2 is operational assuming a 3 month lag compared to Building 1.”
Meta's operational target for the data center
“It is expected to be operational in spring 2027.”