Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · nguồn
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · nguồn
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · nguồn
| Date | Observed status |
|---|---|
| 2023-10-31 | Start of construction for the first building, according to [Applied Digital](https://ir.applieddigital.com/news-events/press-releases/detail/75/applied-digital-announces-groundbreaking-of). CoreWeave |
| 2025-05-28 | CoreWeave signed the first lease package for 250 MW. No buildings online yet. This is according to an [SEC 8-k filing](https://www.sec.gov/Archives/edgar/data/1144879/000164117225013199/form8-k.htm) f |
| 2025-08-29 | [A new 150 MW lease](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with) brings CoreWeave to 400 MW total contracted. The project |
| 2025-10-27 | The first 50 MW slice of Building 1 has reached Ready for Service status according to [this report](https://ir.applieddigital.com/news-events/press-releases/detail/133/applied-digital-achieves-ready-f |
| 2025-11-24 | [This Applied Digital report](https://ir.applieddigital.com/news-events/press-releases/detail/137/applied-digital-completes-phase-ii-ready-for-service-at) says the rest of Building 1 has reached Ready |
| 2026-03-27 | According to satellite imagery, Building 1 looks complete and in service, with the surrounding power/cooling equipment also operational. (Note: this image doesn't provide a view of buildings 2 or 3, t |
| 2026-06-30 | According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and |
| 2026-12-31 | According to the [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 2 should be online sometime in the seco |
| 2027-06-01 | According to [schedule](https://ir.applieddigital.com/news-events/press-releases/detail/128/applied-digital-finalizes-additional-150mw-lease-with), Building 3 should come online in the first half of 2 |
Epoch AI satellite-imagery notes, in date order. · nguồn
Đang xây dựng
Digital infrastructure: AI data-center campus buildout · Kiểm tra 2026-10-30
Chỉ giai đoạn được báo cáo được đánh dấu. Số liệu và ngày tháng phân biệt kế hoạch với kết quả đã chứng minh.
Epoch’s current campus estimate: 68 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 68 MW”
Physical-stage observation dated 2026-06-30. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Building 3 construction is well underway”
Epoch’s dated 2026-06-30 assessment: Building 3 construction is well underway Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Building 3 construction is well underway”
Epoch estimates AI hardware: Nvidia B200 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Nvidia B200 chips.”
Epoch dated observation: CoreWeave was not leased yet at this site, but this is the…
“CoreWeave was not leased yet at this site, but this is the construction start date we're using for relevance.”
Epoch dated observation: According to satellite imagery, Building 2 is fully roofed and shell…
“According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed.”
Ảnh của độc giả, tách biệt với phương tiện có nguồn của ghim. Hãy chấm điểm món bạn đã ăn hoặc thấy, và với ghim nhà hàng, gắn thẻ món ngay trên ảnh của bạn.
Mục đầu tiên luôn là nguồn của ghim. Độ tin cậy tổng thể là trung bình có trọng số về mức độ mỗi tài liệu ủng hộ thời điểm bắt đầu và kết thúc được dùng ở trên; một tài liệu được tính giảm một nửa cho mỗi 180 ngày cũ hơn tài liệu mới nhất.
Ngày đã lưu là điểm đánh dấu theo dõi hoặc quỹ đạo công suất ước tính, không phải là ngày khai trương chính xác đã được xác minh. Tình trạng xây dựng tuân theo phạm vi vật lý được trích dẫn; không có sự hoàn thành nào được suy ra từ các mục tiêu đã trôi qua.
Construction research 2026-10-24: Epoch’s[1] 2026-06-30 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Building 3 construction is well underway” Dated observation 2026-06-30; future trajectory rows and modeled costs are distinguished from this physical milestone.
Thiếu hay sai điều gì? Hãy nói bằng lời của bạn: một liên kết củng cố ghim này, một ngày bắt đầu hoặc kết thúc khác kèm lý do, hoặc một thông tin còn thiếu hay sai. AI đối chiếu với các nguồn của ghim này, tìm nguồn tốt hơn và thêm mọi trang ủng hộ bạn. Các nguồn của chính ghim vẫn được tính nhiều nhất. Hình ảnh thể hiện nội dung khác hoặc thể hiện kém cũng được xem xét, rồi bị hạ xuống hoặc thay thế.
Tiêu đề gốc: CoreWeave Ellendale ND AI Data Center Buildout
Tài liệu quan sát ngày 30-06-2026 của Epoch ghi lại việc xây dựng/lắp đặt vật lý còn lại cho công trình xây dựng được đặt tên này. Đang tiến hành không hoàn thiện các tòa nhà đang vận hành trước đó hoặc công suất trong tương lai. Số lượng công suất và máy gia tốc vẫn là ước tính của Epoch, không phải là xếp hạng được nhà điều hành chứng nhận. Chi phí vốn theo mô hình năm 2025 bao gồm phần cứng máy tính và không phải là ngân sách xây dựng nguồn gốc.
Cơ sở đào tạo và suy luận AI biên giới siêu quy mô được Epoch AI theo dõi với dấu chân vệ tinh được chú thích (8 phần vật lý).