Residential construction · Kiểm tra 2026-10-30
Chỉ giai đoạn được báo cáo được đánh dấu. Số liệu và ngày tháng phân biệt kế hoạch với kết quả đã chứng minh.
About $47 million (range $38.6 million–$56.6 million): 92 units at $420,000–$615,000 per unit. An estimate, not a published budget; excludes land, soft costs and financing.
“California (LA, Bay, San Diego) $420k–$615k/unit Highest US wood-frame cost.”
16 subsidized and 76 market-rate apartments in a seven-story building.
“The new project will include 16 subsidized apartments mixed in with the 76 market-rate units.”
Benchmark for California (Los Angeles, Bay Area, San Diego) wood-frame podium projects.
“California (LA, Bay, San Diego) $420k–$615k/unit Highest US wood-frame cost.”
Top of the same published range.
“California (LA, Bay, San Diego) $420k–$615k/unit Highest US wood-frame cost.”
Low: 92 × $420,000 = $38,640,000. High: 92 × $615,000 = $56,580,000.
92 × $517,500 (midpoint per unit) = $47,610,000, the midpoint ($47,610,000) rounded to $47 million.
Land, design and permit fees, financing and the developer fee. The benchmark is for new wood-frame construction; the structural system and the cost of restoring the historic building are not published, so the real figure could differ. This is an estimate of vertical building cost, not a published budget.
Roughly 4,900 sq ft, plus one level of underground parking with 23 spaces
“It also calls for one level of underground parking with 23 spots, and roughly 4,900 square feet of commercial space on the ground level.”
92 units in a seven-story building: 16 subsidized, 76 market rate
“The new project will include 16 subsidized apartments mixed in with the 76 market-rate units.”
September 2027 to March 2028 (18 to 24 months after March 2026), per the developer; no completion date published
“Cadieux said construction will likely not happen for another 18 to 24 months because of additional planning and permits.”
Approved 6-0 by the Planning Commission on March 19, 2026; environmental appeal to the City Council (hearing June 30, 2026, outcome not reported); construction not started
“On June 30, the San Diego City Council will consider the claims of inadequate environmental review.”
Historical Resource Board review
“It also went to the city’s Historical Resource Board in late February, where it received high marks for its preservation of the lower levels.”
Planning Commission approves 6-0
“The project was approved 6-0 with little fanfare”
SAFER files environmental appeal
“In its March 31 appeal, SAFER alleges that developer Nathan Cadieux and his firm Purpose”
City Council hearing on the appeal (outcome not found)
“On June 30, the San Diego City Council will consider the claims of inadequate environmental review.”
Estimated construction start
“Cadieux said construction will likely not happen for another 18 to 24 months because of additional planning and permits.”
“I think the big win for the city, and the community, is it is an example of how to build density,” he said, “while also respecting these character-defining buildings in our neighborhoods.”
In its March 31 appeal, SAFER alleges that developer Nathan Cadieux and his firm Purpose did not conduct proper environmental review.
Some don’t see SAFER’s motivations as entirely out of concern for a development’s potential impacts on traffic or air quality.
| Developer Nate Cadieux after the Planning Commission vote (via Carrier Johnson + Culture) · 19 thg 3, 2026 | 0.80 |
|---|---|
| SAFER's appeal alleges inadequate environmental review (Times of San Diego) · 23 thg 6, 2026 | -0.70 |
| Skepticism about the appellant's motives (Times of San Diego) · 24 thg 6, 2026 | 0.30 |
Ảnh của độc giả, tách biệt với phương tiện có nguồn của ghim. Hãy chấm điểm món bạn đã ăn hoặc thấy, và với ghim nhà hàng, gắn thẻ món ngay trên ảnh của bạn.
Mục đầu tiên luôn là nguồn của ghim. Độ tin cậy tổng thể là trung bình có trọng số về mức độ mỗi tài liệu ủng hộ thời điểm bắt đầu và kết thúc được dùng ở trên; một tài liệu được tính giảm một nửa cho mỗi 180 ngày cũ hơn tài liệu mới nhất.
Nhà phát triển Nate Cadieux cho biết vào ngày 19 tháng 3 năm 2026 rằng việc xây dựng có thể sẽ không bắt đầu trong 18 đến 24 tháng nữa, tức là từ tháng 9 năm 2027 đến tháng 3 năm 2028; ngày hiển thị là ngày bắt đầu của khoảng thời gian đó và kết quả kháng nghị vẫn chưa được xác định.
Planning Commission 6-0 approval, 16/76 unit split, parking, retail area, address, 18-24 month start estimate.[1]
Context on the appellant's motives and the council's two options.[1]
Regional per-unit cost benchmark ($420k-$615k, vertical hard cost) behind the estimated price; not specific to this project.[1]
Thiếu hay sai điều gì? Hãy nói bằng lời của bạn: một liên kết củng cố ghim này, một ngày bắt đầu hoặc kết thúc khác kèm lý do, hoặc một thông tin còn thiếu hay sai. AI đối chiếu với các nguồn của ghim này, tìm nguồn tốt hơn và thêm mọi trang ủng hộ bạn. Các nguồn của chính ghim vẫn được tính nhiều nhất. Hình ảnh thể hiện nội dung khác hoặc thể hiện kém cũng được xem xét, rồi bị hạ xuống hoặc thay thế.
Tiêu đề gốc: Newman Building Redevelopment (North Park)
Chưa có ngân sách xây dựng nào được công bố nên giá của chốt là ước tính được xây dựng từ các bộ phận sau:
Các hình ảnh chính là bản vẽ của tòa nhà được đề xuất, được xuất bản với phạm vi đưa tin của Ủy ban Kế hoạch; bức ảnh thứ ba cho thấy tòa nhà ngày nay.