Ghim này theo sát tin tức: nó cho thấy những gì hiện đã biết, và đây là điều đã thay đổi cùng nguyên nhân.
Đã chỉnh sửabởi @ThePinGang
Trước
2027. Equinor identifies an expected commercial-operation date in 2027 for Empire Wind 1.
Construction is verified; the completion date remains an estimate. The timeline marker represents the published target year/month, not a confirmed opening day.
Equinor describes total Empire Wind capital expenditure estimated at $5 billion after tax credits, covering 54 bottom-fixed turbines and the Brooklyn cable landfall. This is a tax-credit-adjusted estimate, not gross pre-credit cost and not the over-$3 billion financing package. Empire Wind 1 has an 810 MW generation rating and documented offshore construction; full operation is targeted for 2027.
Equinor January 2, 2025 publishes approximately USD5 billion expected total capital investment, including South Brooklyn Marine Terminal use fees and the effect of expected future investment tax credits. The financing package above USD3 billion is separate. Published electric generating project rating for Empire Wind 1: 810 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Official project announcement identifies 810 MW and distinguishes financing from project capital expenditure.
Empire Wind’s operator construction page shows offshore installation and identifies the substation installed in January 2026. Empire Wind 1 is expected to be fully operational in 2027. The offshore site and South Brooklyn Marine Terminal serve different functions; the terminal is not the generation site.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Empire Wind offshore substation installation image published in the operator construction gallery; the page identifies installation in January 2026. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Operator source page; original image.
Empire Wind offshore substation installation image published in the operator construction gallery; the page identifies installation in January 2026. Credit: Empire Wind / Equinor; photographer not named on source page. Operator source page; original image.
Đã chỉnh sửabởi @ThePinGang
Đã chỉnh sửabởi @ThePinGang
Trước
Trước
Equinor describes total Empire Wind capital expenditure estimated at $5 billion after tax credits, covering 54 bottom-fixed turbines and the Brooklyn cable landfall. This is a tax-credit-adjusted estimate, not gross pre-credit cost and not the over-$3 billion financing package. Empire Wind 1 has an 810 MW generation rating and documented offshore construction; full operation is targeted for 2027.
Equinor January 2, 2025 publishes approximately USD5 billion expected total capital investment, including South Brooklyn Marine Terminal use fees and the effect of expected future investment tax credits. The financing package above USD3 billion is separate. Published electric generating project rating for Empire Wind 1: 810 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Official project announcement identifies 810 MW and distinguishes financing from project capital expenditure.
Empire Wind’s operator construction page shows offshore installation and identifies the substation installed in January 2026. Empire Wind 1 is expected to be fully operational in 2027. The offshore site and South Brooklyn Marine Terminal serve different functions; the terminal is not the generation site.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Empire Wind offshore substation installation image published in the operator construction gallery; the page identifies installation in January 2026. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Operator source page; original image.
Empire Wind offshore substation installation image published in the operator construction gallery; the page identifies installation in January 2026. Credit: Empire Wind / Equinor; photographer not named on source page. Operator source page; original image.
Đã chỉnh sửabởi @ThePinGang
Trước
Equinor describes total Empire Wind capital expenditure estimated at $5 billion after tax credits, covering 54 bottom-fixed turbines and the Brooklyn cable landfall. This is a tax-credit-adjusted estimate, not gross pre-credit cost and not the over-$3 billion financing package. Empire Wind 1 has an 810 MW generation rating and documented offshore construction; full operation is targeted for 2027.
Equinor January 2, 2025 publishes approximately USD5 billion expected total capital investment, including South Brooklyn Marine Terminal use fees and the effect of expected future investment tax credits. The financing package above USD3 billion is separate. Published electric generating project rating for Empire Wind 1: 810 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Official project announcement identifies 810 MW and distinguishes financing from project capital expenditure.
Empire Wind’s operator construction page shows offshore installation and identifies the substation installed in January 2026. Empire Wind 1 is expected to be fully operational in 2027. The offshore site and South Brooklyn Marine Terminal serve different functions; the terminal is not the generation site.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Empire Wind offshore substation installation image published in the operator construction gallery; the page identifies installation in January 2026. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Operator source page; original image.
Đã chỉnh sửabởi @ThePinGang
Trước
Equinor describes total Empire Wind capital expenditure estimated at $5 billion after tax credits, covering 54 bottom-fixed turbines and the Brooklyn cable landfall. This is a tax-credit-adjusted estimate, not gross pre-credit cost and not the over-$3 billion financing package. Empire Wind 1 has an 810 MW generation rating and documented offshore construction; full operation is targeted for 2027.
Equinor January 2, 2025 publishes approximately USD5 billion expected total capital investment, including South Brooklyn Marine Terminal use fees and the effect of expected future investment tax credits. The financing package above USD3 billion is separate. Published electric generating project rating for Empire Wind 1: 810 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Official project announcement identifies 810 MW and distinguishes financing from project capital expenditure.
Empire Wind’s operator construction page shows offshore installation and identifies the substation installed in January 2026. Empire Wind 1 is expected to be fully operational in 2027. The offshore site and South Brooklyn Marine Terminal serve different functions; the terminal is not the generation site.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Empire Wind offshore substation installation image published in the operator construction gallery; the page identifies installation in January 2026. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Đã chỉnh sửabởi @ThePinGang
Trước
Trước
Empire Wind’s operator construction page shows offshore installation and identifies the substation installed in January 2026. Empire Wind 1 is expected to be fully operational in 2027. The offshore site and South Brooklyn Marine Terminal serve different functions; the terminal is not the generation site.
Operator project overview confirms permitting and development context.
EIA August 2026 generator inventory, plant ID 68443: Empire Wind 1, Kings County, NY. Included 1 new/recent generating units with a summed nameplate rating of 810 MW.
EIA reports operation at month/year precision. The date is the last day of the earliest reported operation month/year, an estimated display boundary, not an exact opening day. Different units may have later dates. Future dates are operator-reported plans, not guarantees.
Coordinates are the EIA-reported plant point, not a verified entrance. New units at existing plants are included; the total excludes older units and battery/pumped storage. Capacity is a power rating, not annual energy output. Status was reported in August and may have changed since.
GEM August 2026 snapshot: under construction. 816 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Wind.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Empire Wind offshore substation installation image published in the operator construction gallery; the page identifies installation in January 2026. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Additional source view; compare phase coverage and rating conventions before combining figures.
Đã chỉnh sửabởi @ThePinGang
Trước
Empire Wind’s operator construction page shows offshore installation and identifies the substation installed in January 2026. Empire Wind 1 is expected to be fully operational in 2027. The offshore site and South Brooklyn Marine Terminal serve different functions; the terminal is not the generation site.
Operator project overview confirms permitting and development context.
EIA August 2026 generator inventory, plant ID 68443: Empire Wind 1, Kings County, NY. Included 1 new/recent generating units with a summed nameplate rating of 810 MW.
EIA reports operation at month/year precision. The date is the last day of the earliest reported operation month/year, an estimated display boundary, not an exact opening day. Different units may have later dates. Future dates are operator-reported plans, not guarantees.
Coordinates are the EIA-reported plant point, not a verified entrance. New units at existing plants are included; the total excludes older units and battery/pumped storage. Capacity is a power rating, not annual energy output. Status was reported in August and may have changed since.
GEM August 2026 snapshot: under construction. 816 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Wind.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
Offshore installation photograph from Empire Wind’s operator project page. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Empire Wind offshore substation installation image published in the operator construction gallery; the page identifies installation in January 2026. Credit: Empire Wind / Equinor; photographer not named on source page. Source page; original operator image.
Đây là ảnh của độc giả, tách riêng khỏi phương tiện có nguồn của ghim.
Mục đầu tiên luôn là nguồn của ghim. Độ tin cậy tổng thể là trung bình có trọng số về mức độ mỗi tài liệu ủng hộ thời điểm bắt đầu và kết thúc được dùng ở trên; một tài liệu được tính giảm một nửa cho mỗi 180 ngày cũ hơn tài liệu mới nhất.
Mục tiêu được công bố: 2027. Việc xây dựng đã được ghi nhận, nhưng cột mốc hoàn thành/vận hành trong tương lai này chỉ là ước tính. Ngày này là mốc cuối năm/tháng trên dòng thời gian, không phải ngày khai trương được xác nhận. Nguồn: https://www.equinor[2].com/news/20250102-securing-financial-close-empire-wind[3]-1
Equinor January 2, 2025 publishes approximately USD5 billion expected total capital investment, including South Brooklyn Marine Terminal use fees and the effect of expected future investment tax credits. The financing package above USD3 billion is separate. Published electric generating project rating for Empire Wind[3] 1: 810 MW. Basis: Operator-reported electric generating capacity; not annual energy production. Official project announcement identifies 810 MW and distinguishes financing from project capital expenditure.
Empire Wind’s operator construction page shows offshore installation and identifies the substation installed in January 2026. Empire Wind 1 is expected to be fully operational in 2027. The offshore site and South Brooklyn Marine Terminal serve different functions; the terminal is not the generation site.
Thiếu hay sai điều gì? Hãy nói bằng lời của bạn: một liên kết củng cố ghim này, một ngày bắt đầu hoặc kết thúc khác kèm lý do, hoặc một thông tin còn thiếu hay sai. AI đối chiếu với các nguồn của ghim này, tìm nguồn tốt hơn và thêm mọi trang ủng hộ bạn. Các nguồn của chính ghim vẫn được tính nhiều nhất. Hình ảnh thể hiện nội dung khác hoặc thể hiện kém cũng được xem xét, rồi bị hạ xuống hoặc thay thế.
Tiêu đề gốc: Empire Wind 1 — estimated target 2027
2027. Equinor nêu ngày vận hành thương mại dự kiến vào năm 2027 cho Empire Wind 1.[2]
Việc xây dựng đã được xác minh; ngày hoàn thành vẫn là ước tính. Mốc trên dòng thời gian thể hiện năm/tháng mục tiêu đã công bố, không phải ngày khai trương đã được xác nhận.
Equinor mô tả tổng chi đầu tư của Empire Wind ước tính 5 tỷ đô la sau tín dụng thuế, bao gồm 54 tuabin móng cố định và điểm đưa cáp lên bờ tại Brooklyn. Đây là ước tính đã điều chỉnh theo tín dụng thuế, không phải chi phí gộp trước tín dụng và cũng không phải gói tài trợ trên 3 tỷ đô la. Empire Wind 1 có công suất phát điện 810 MW và việc xây dựng ngoài khơi đã được ghi nhận; vận hành đầy đủ được đặt mục tiêu vào năm 2027.[2][3]
Ngày 2 tháng 1 năm 2025, Equinor công bố tổng vốn đầu tư dự kiến khoảng 5 tỷ USD, bao gồm phí sử dụng South Brooklyn Marine Terminal và tác động của các khoản tín dụng thuế đầu tư dự kiến trong tương lai. Gói tài trợ trên 3 tỷ USD là khoản riêng. Công suất dự án phát điện được công bố cho Empire Wind 1: 810 MW. Cơ sở: công suất phát điện do đơn vị vận hành báo cáo; không phải sản lượng năng lượng hằng năm. Thông báo chính thức của dự án nêu 810 MW và phân biệt tài trợ với chi đầu tư của dự án.[2]
Trang thi công của đơn vị vận hành Empire Wind cho thấy việc lắp đặt ngoài khơi và cho biết trạm biến áp được lắp đặt vào tháng 1 năm 2026. Empire Wind 1 dự kiến vận hành đầy đủ vào năm 2027. Khu vực ngoài khơi và South Brooklyn Marine Terminal có chức năng khác nhau; cảng này không phải nơi phát điện.[3]
Chỉ giữ lại các dự án có việc xây dựng thực tế, chạy thử hoặc khai trương năm 2025–2026 được ghi nhận, cùng chi phí và công suất điện riêng của dự án đã công bố. Chi phí dùng phạm vi và đơn vị tiền tệ đã công bố; không có ước tính tham chiếu hay quy đổi tiền tệ. MW là công suất, không phải sản lượng điện hằng năm. Sản lượng năng lượng hằng năm dự kiến, nếu có, là dự báo. Điểm trên bản đồ là vị trí nhà máy/dự án được báo cáo và có thể chỉ là gần đúng. Các chế độ xem kiểm kê trùng khớp và đề xuất mở rộng bị loại không phải công suất có thể cộng dồn.
Ảnh chụp công tác lắp đặt ngoài khơi từ trang dự án của đơn vị vận hành Empire Wind. Ghi công: Empire Wind / Equinor; trang nguồn không nêu tên nhiếp ảnh gia. Trang nguồn; ảnh gốc của đơn vị vận hành.
Hình ảnh lắp đặt trạm biến áp ngoài khơi của Empire Wind được đăng trong thư viện thi công của đơn vị vận hành; trang này cho biết việc lắp đặt diễn ra vào tháng 1 năm 2026. Ghi công: Empire Wind / Equinor; trang nguồn không nêu tên nhiếp ảnh gia. Trang nguồn; ảnh gốc của đơn vị vận hành.
Ảnh chụp công tác lắp đặt ngoài khơi từ trang dự án của đơn vị vận hành Empire Wind. Ghi công: Empire Wind / Equinor; trang nguồn không nêu tên nhiếp ảnh gia. Trang nguồn của đơn vị vận hành; ảnh gốc.
Hình ảnh lắp đặt trạm biến áp ngoài khơi của Empire Wind được đăng trong thư viện thi công của đơn vị vận hành; trang này cho biết việc lắp đặt diễn ra vào tháng 1 năm 2026. Ghi công: Empire Wind / Equinor; trang nguồn không nêu tên nhiếp ảnh gia. Trang nguồn của đơn vị vận hành; ảnh gốc.
Lớp đá dưới nước quanh một móng của Empire Wind. Ngày chụp không được nêu riêng. Ghi công: Empire Wind / Equinor; không nêu tên nhiếp ảnh gia. Nguồn và thư viện ảnh; tệp gốc.
Công việc cáp nội bộ giữa các tuabin của Empire Wind, từ thư viện chính thức về lắp đặt ngoài khơi. Ngày chụp không được nêu riêng. Ghi công: Empire Wind / Equinor; không nêu tên nhiếp ảnh gia. Nguồn và thư viện ảnh; tệp gốc.