TVA’s planned six-unit Allen aeroderivative addition, shown in the April 2025 public meeting materials, PDF page 10. This is an official design rendering, not a photograph of operating equipment.[1]
TVA June 30, 2026 Form 10-Q discloses $276 million spent and up to $155 million additional spending on its 200 MW Allen aeroderivative addition. Sum: up to $431 million, explicitly calculated from published project figures. This is an upper forecast spending envelope, not a quoted fixed-price contract. Allen aeroderivative addition: published generating capacity 200 MW. Operator-reported electric generating capacity; not annual energy production TVA explicitly reports constructing this 200 MW project after a December 2025 air permit. The planning-only Lagoon Creek project is separate and excluded.[1]
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
原标题: Allen aeroderivative addition — under construction
TVA 2026年6月30日的Form 10-Q披露,其200兆瓦艾伦航改机组扩建已支出2.76亿美元,另需追加支出最高1.55亿美元。合计最高4.31亿美元,由已公布的项目数据明确计算得出。这是预测支出的上限区间,并非所引用的固定价格合同。[3]
TVA 2026年6月30日的10-Q表格披露,其200 MW艾伦航改型机组扩建项目已支出2.76亿美元,另有最多1.55亿美元的追加支出。合计:最多4.31亿美元,由已公布的项目数据明确计算得出。这是预测支出的上限,并非已引用的固定价格合同。艾伦航改型机组扩建:公布的发电装机容量为200 MW。运营商报告的发电装机容量;并非年发电量。TVA明确表示,在2025年12月获得空气许可后,正在建设这一200 MW项目。仅处于规划阶段的Lagoon Creek项目另行处理,不在此列。[3]
仅保留有实体施工、调试或2025–2026年投运记录,且已公布项目专属成本和电力输出的项目。成本采用已公布的范围和货币;不使用基准估算或货币换算。MW为功率容量,而非年发电量。如有预期年发电量,则为预测值。地图上的点为所报告的电厂/项目位置,可能为大致位置。匹配的清单视图和被排除的扩建提案不属于可叠加的容量。
TVA规划的六机组艾伦航改型机组扩建项目,见于2025年4月公众会议材料PDF第10页。这是官方设计效果图,不是运行中设备的照片。署名:Tennessee Valley Authority;未注明作者。来源与图库;原始媒体。
TVA艾伦厂址位置及拟议的航改型机组设计,2025年4月会议材料PDF第3页。带标注的航拍图区分了已退役的燃煤电厂、现有的联合循环电厂和新的航改型机组厂址。署名:Tennessee Valley Authority;底图航拍图像的署名未单独说明。来源与图库;原始媒体。