第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
有记录的实体里程碑或带日期的进展/报告节点。期末日期仅代表所报告的月份/季度,不会虚构确切的投运日期。来源中的估计值均已标注,不视为已确认的未来开业日期。
Steady development at the Sofia array, with over 80 turbines now installed (May 2026). Official project gallery photograph; the date is the operator’s gallery label.[1]
RWE[4] Q1 2021 publishes anticipated project investment of approximately £3 billion for Sofia, including the grid connection that must be sold after completion. Published generating capacity is 1,400 MW. This is the original investment-decision estimate, not a newly calculated 2026 budget. Sofia offshore wind farm: 1400 MW generating project rating. Operator-reported electric generating capacity; not annual energy production
RWE[3] June 11, 2026 confirms installation of all 100 × 14 MW turbines, final turbine installation June 10. Construction/commissioning continues; the announcement does not prove full commercial operation.
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
原标题: Sofia offshore wind farm — under construction / commissioning
RWE 2021年第一季度报告公布Sofia的预期项目投资约为30亿英镑,其中包括完工后须出售的电网接入部分。公布的发电容量为1,400 MW。这是最初的投资决策估算,而非重新计算的2026年预算。[3][4]
RWE 2021年第一季度报告公布Sofia的预期项目投资约为30亿英镑,其中包括完工后须出售的电网接入部分。公布的发电容量为1,400 MW。这是最初的投资决策估算,而非重新计算的2026年预算。Sofia海上风电场:发电项目额定容量为1400 MW。运营商报告的发电装机容量;并非年发电量[3]
RWE于2026年6月11日确认,全部100台14 MW涡轮机(100 × 14 MW)已安装完毕,最后一台于6月10日安装。建设/调试仍在继续;该公告不能证明已全面商业运营。[4]
仅保留有实体施工、调试或2025–2026年投运记录,且已公布项目专属成本和电力输出的项目。成本采用已公布的范围和货币;不使用基准估算或货币换算。MW为功率容量,而非年发电量。如有预期年发电量,则为预测值。地图上的点为所报告的电厂/项目位置,可能为大致位置。匹配的清单视图和被排除的扩建提案不属于可叠加的容量。
Sofia风电阵列稳步推进,目前已安装超过80台涡轮机(2026年5月)。项目官方图库照片;日期为运营商的图库标注。图片来源: RWE / Sofia Offshore Wind Farm;此图片的摄影师未注明。来源与图库;原始媒体。
最后一座涡轮机塔筒正在装载,准备出海(2026年6月)。项目官方图库照片;日期为运营商的图库标注。图片来源: RWE / Sofia Offshore Wind Farm;此图片的摄影师未注明。来源与图库;原始媒体。