Documented physical milestone or dated progress/reporting marker. Period-end dates represent only the reported month/quarter; they do not invent an exact operation date. Source estimates are labelled and not treated as confirmed future opening dates.
The OPEC Fund’s project record publishes total project cost US$2,249.60 million. It covers the multipurpose dam programme, including water supply, irrigation and flood-control works, not just the power station. The Fund’s loan is not used as project cost. Mohmand multipurpose dam and hydropower project: 800 MW generating project rating. Operator-reported electric generating capacity; not annual energy production
WAPDA’s[4] current project page identifies 800 MW installed design capacity, ongoing construction, river diversion November 2024, dam impounding targeted late 2026 and electricity generation early 2028. Targets are not completion claims.
WAPDA[3] January 19, 2026 reports construction continuing on ten key sites.
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
The OPEC Fund’s project record publishes total project cost US$2,249.60 million. It covers the multipurpose dam programme, including water supply, irrigation and flood-control works, not just the power station. The Fund’s loan is not used as project cost.[2][3][4]
The OPEC Fund’s project record publishes total project cost US$2,249.60 million. It covers the multipurpose dam programme, including water supply, irrigation and flood-control works, not just the power station. The Fund’s loan is not used as project cost. Mohmand multipurpose dam and hydropower project: 800 MW generating project rating. Operator-reported electric generating capacity; not annual energy production[2]
WAPDA’s current project page identifies 800 MW installed design capacity, ongoing construction, river diversion November 2024, dam impounding targeted late 2026 and electricity generation early 2028. Targets are not completion claims.[3]
WAPDA January 19, 2026 reports construction continuing on ten key sites.[4]
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.