已宣布
Energy: battery storage · 核查日期 2026-10-30
仅突出显示已报告的阶段。数据和日期区分规划与已验证状态。
500 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"Stein - Rapson 345 kV line","summerNetMW":500.0”
2025-04-01; requested date only, not an achieved opening.
“"projectNumber":"J2590","queueDate":"2022-09-15T04:00:00+00:00","inService":"2025-04-01T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":"Not Started"”
Battery Storage; Stein - Rapson 345 kV line.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J2590","queueDate":"2022-09-15T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J2590","queueDate":"2022-09-15T04:00:00+00:00","inService":"2025-04-01T04:00:00+00:00"”
这个标记会跟进新闻:它显示目前已知的情况,这里列出改了什么以及起因。
已编辑由 @ThePinGang
ITC Michigan and MISO have advanced system stability and generator interconnection engineering for the 500M USD, 500 MW / 2,000 MWh Stein-Rapson Clean Energy Storage Center in Huron County, Michigan.J2590 is a 500 MW battery storage interconnection request in Huron, MI. The grid operator lists its queue status as Active. The requested in-service date is 2025-04-01; this is a planning date.
ITC Michigan progressed MISO DPP Definitive Planning Study Queue J2140 engineering for the facility. Features 500 MW / 2,000 MWh of utility-grade containerized lithium iron phosphate battery storage. Represents an estimated 500 million USD private clean energy development in Michigan's Thumb region. Interconnects to ITC Michigan's 345 kV Stein to Rapson transmission line. Captures high-volume Thumb wind and solar generation, resolving regional transmission bottlenecks. Timeline: planned project targeting commercial operation in August 2029 (estimated) under MISO interconnection queue and state regulatory schedules.J2590 is a 500 MW battery storage interconnection request in Huron, MI. The grid operator lists its queue status as Active. The requested in-service date is 2025-04-01; this is a planning date. The point of interconnection is Stein - Rapson 345 kV line. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
已编辑由 @ThePinGang
… wind and solar generation, resolving regional transmission bottlenecks. Timeline: planned project targeting commercial operation in August 2029 (estimated) under MISO interconnection queue and state regulatory schedules.
读者上传的照片,与图钉带来源的媒体分开显示。你可以为吃到或看到的内容评分,在餐厅图钉上还能直接在照片上标记菜品。
第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
2025年4月1日是互联记录要求的投入使用日期,不是经过验证的开通或商业运营日期。
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
原标题: Stein-Rapson: 500 MW Battery Interconnection Request J2590
Power storage500 MW · J2590: 500 MW requested battery storage. Queue status: Active. Requested date: 2025-04-01. Not current measured generation; No annual energy or battery MWh inferred. · source