第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
该引脚的 2028 年 3 月“商业运营”日期没有来源(商会第 404 页)。尚未公布破土动工或完成目标,且该项目尚未获得理事会批准(2027 年 4 月 13 日决定),因此日期保持不变,由协调员决定。
Tracker listing: permitted, 50 MW planned (aggregator, secondary).[1]
Cited in the project timeline.[1]
Cited in the project timeline.[1]
Cited in the project timeline.[1]
About 50 MW
“Raeden predicts the data center will draw about 50 megawatts, which they say is less than most data centers.”
13 April 2027 (City Council)
“The council voted 7-2 to postpone a final decision on whether to approve the proposed data center until April 13, 2027”
Planning Commission denied appeals 23 July 2026; Council decision postponed to 13 April 2027
“The council voted 7-2 to postpone a final decision on whether to approve the proposed data center until April 13, 2027”
Raeden's Project Taurus plan reported near Garden of the Gods
“Raeden predicts the data center will draw about 50 megawatts, which they say is less than most data centers.”
Planning Commission hearing; 6-2 vote denying appeals, with added conditions
“Last month, the Colorado Springs Planning Commission voted six to two to deny appeals against the proposed data center.”
Two appeals filed, sending decision to City Council
“Last month, the Colorado Springs Planning Commission voted six to two to deny appeals against the proposed data center.”
City Council votes 7-2 to postpone decision
“The council voted 7-2 to postpone a final decision on whether to approve the proposed data center until April 13, 2027”
City Council decision on appeals postponed to
“The council voted 7-2 to postpone a final decision on whether to approve the proposed data center until April 13, 2027”
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
原标题: Raeden Project Taurus Data Center Campus: 400M USD, 53 MW Computing Facility in El Paso County, Colorado
金牛座项目是 Raeden 提议的 50 兆瓦数据中心,位于科罗拉多斯普林斯西北部高科技路 1565 号,重新利用了众神花园路和百年大道附近的前英特尔芯片工厂。规划委员会于 2026 年 7 月 23 日驳回上诉,随后向市议会提出了两项上诉,并于 2026 年 9 月 17 日以 7 比 2 的投票结果将其决定推迟至 2027 年 4 月 13 日。没有施工报告。