Energy: battery storage · 核查日期 2026-10-30
仅突出显示已报告的阶段。数据和日期区分规划与已验证状态。
200 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"BEACON","summerNetMW":200.0”
2027-09-10; requested date only, not an achieved opening.
“"projectNumber":"J3551","queueDate":"2024-04-18T04:00:00+00:00","inService":"2027-09-10T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":""”
Battery Storage; BEACON.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J3551","queueDate":"2024-04-18T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J3551","queueDate":"2024-04-18T04:00:00+00:00","inService":"2027-09-10T04:00:00+00:00"”
这个标记会跟进新闻:它显示目前已知的情况,这里列出改了什么以及起因。
已编辑由 @ThePinGang
MISO regional transmission interconnection development of the Beacon Clean Energy Storage Facility in Mahaska County, Iowa. SupplyingJ3551 is a 200 MW / 800 MWh of lithium-ion energy storage, the facility connects to regional transmission lines near Oskaloosa to absorb surplus wind generation and strengthen southeastern Iowa electrical infrastructure.battery storage interconnection request in Mahaska, IA. The grid operator lists its queue status as Active. The requested in-service date is 2027-09-10; this is a planning date.
Developers progressed regulatory filings for the Beacon Clean Energy Storage Facility near OskaloosaJ3551 is a 200 MW battery storage interconnection request in Mahaska County, Iowa. Supplies 200 MW / 800 MWh of grid-scale four-hour battery energy storage. Represents an estimated 210 million USD private clean power investment in southeastern Iowa. Connects to regional high-voltage transmission lines within the MISO market footprint. Absorbs surplus regional wind generation and provides dispatchable capacity during peak demand periods. Timeline: planned project targeting commercial operation in September 2027 (estimated) under MISO interconnection queue and state regulatory schedules.Mahaska, IA. The grid operator lists its queue status as Active. The requested in-service date is 2027-09-10; this is a planning date. The point of interconnection is BEACON. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
已编辑由 @ThePinGang
… and provides dispatchable capacity during peak demand periods. Timeline: planned project targeting commercial operation in September 2027 (estimated) under MISO interconnection queue and state regulatory schedules.
读者上传的照片,与图钉带来源的媒体分开显示。你可以为吃到或看到的内容评分,在餐厅图钉上还能直接在照片上标记菜品。
第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
原标题: Beacon: 200 MW Battery Interconnection Request J3551
Power storage200 MW · J3551: 200 MW requested battery storage. Queue status: Active. Requested date: 2027-09-10. Not current measured generation; No annual energy or battery MWh inferred. · source