About 100 acres of ERCOR's land (500-acre property per Times-Tribune; 548 acres per WVIA)
“The data centers would encompass about 100 acres of ERCOR’s land, LaFratte said.”
Proposed; no data center approved, no final decision made
“No final decision has been made on the proposed data centers.”
Nine data centers (ERCOR Triboro); DeNaples seven-building plan withdrawn
“There are now nine data centers proposed in the borough after ERCOR Triboro, a limited liability company under St. Louis-based Sansone Group, applied to change its land use from four 1-million-square-foot warehouses.”
Sansone Group buys about 500 acres from DeNaples (price reported as $80 million)
“Sansone bought 500 acres from DeNaples last year for $80 million.”
Council adopts then denies data center zoning amendment (CM-2 conditional use)
“Council initially adopted but then denied the zoning amendment addressing data centers amid uproar from the crowd.”
There’s anger, there’s resentment, frustration, because we go to these meetings and it feels like we’re not being heard,
That ordinance was well thought out. It was developed over eight months.
Grossman and PPL Spokesperson Dana Burns both said there are nondisclosure agreements in place
| PPL Electric Utilities confirms data centers spurred transmission project in Lackawanna County · 2026年4月22日 | -0.20 |
|---|---|
| Olyphant settles DeNaples lawsuit and confirms data center regulations · 2026年6月10日 | 0.20 |
| Olyphant residents rally over proposed TriBoro data centers · 2026年8月3日 | -0.70 |
这个标记会跟进新闻:它显示目前已知的情况,这里列出改了什么以及起因。
已编辑由 @ThePinGang
Olyphant received two separate data-center proposals:A June 10, 2026 report says Triboro Commerce Park LLC sought seven buildings on over 400 acres, whilewithdrew its seven-building plan. A separate ERCOR Triboro proposed proposal sought nine buildings on roughly 500 adjacent acres.data centers on a 500-acre property.
Olyphant received two separate data-center proposals:Olyphant’s engineer confirmed withdrawal of Triboro Commerce Park LLC sought seven buildings on over 400 acres, while ERCOR TriboroPark’s seven-building plan. ERCOR Triboro, a Sansone Group company, separately proposed nine buildings on roughly 500 adjacent acres. The proposals have separate developers and applications. A combined 1,500 MW capacity, USD 14.25 billion construction budget and achieved construction milestone aredata centers, occupying about 100 acres of its 500-acre property. The zoning settlement did not established by this report.approve a campus.
已编辑由 @ThePinGang
Two separate developers are separately proposing to build 16 data centers in total east of the Casey Highway. \n First, in early April,Olyphant received two separate data-center proposals: Triboro Commerce Park LLC, a company associated with DeNaples, submitted a plan to develop 7 data centersLLC sought seven buildings on just over 400 acres of the roughly 1,000-acre CM-2 zone. In late April, the company also filed a land-use appeal and a petition for an emergency injunction in Lackawanna County Court of Common Pleas asking the court to overturn Olyphant Borough Council's decision declaring its zoning ordinance invalid via a curative amendment, citing the action unlawfully excludes data centers — a further signal of its intent to build. \n Then, on May 4, Olyphant received a zoning application fromacres, while ERCOR Triboro, a limited liability company under Sansone Group, to change its land use from four warehouses toTriboro proposed nine data centers. Their campus spans aboutbuildings on roughly 500 acres and is adjacent to DeNaples land.acres.
Electrical Load: 1,500 MW planned utility capacity Olyphant received two separate data-center proposals: Triboro Commerce Park LLC sought seven buildings on the Pennsylvania / PJM grid. Site & Facility Footprint: 900 acres in Olyphant Borough, Lackawanna County, Pennsylvania. Water Demand: 1.80 MGD (estimated).over 400 acres, while ERCOR Triboro proposed nine buildings on roughly 500 adjacent acres. The proposals have separate developers and applications. A combined 1,500 MW capacity, USD 14.25 billion construction budget and achieved construction milestone are not established by this report.
读者上传的照片,与图钉带来源的媒体分开显示。你可以为吃到或看到的内容评分,在餐厅图钉上还能直接在照片上标记菜品。
第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
Pin 日期 2026-06-10 与《时代论坛报》的报道相符。ERCOR 的申请日期没有给出;未公布完成目标。
Cited in the project timeline.[1]
Cited in the project timeline.[1]
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
原标题: Olyphant Triboro Plans: DeNaples Proposal Withdrawn, ERCOR Proposal Separate
拉克万纳县奥利芬特区有一个占地约 1,000 英亩的分区,数据中心是有条件使用的。Triboro Commerce Park 的 7 个数据中心计划于 2026 年 6 月被撤回,而 Sansone 集团旗下公司 ERCOR Triboro 申请在其约 100 英亩的土地上建设 9 个数据中心。市议会 2026 年 6 月的解决方案并未批准任何校园建设,居民们正在组织起来反对该计划。
Olyphant 的工程师确认撤回 Triboro 商业园的七栋建筑计划。Sansone Group 旗下公司 ERCOR Triboro 分别提议建设 9 个数据中心,占用其 500 英亩土地中的约 100 英亩。分区协议并未批准设立校园。[1]
Council votes 6-0 to settle Triboro Commerce Park lawsuit; amendment recognized
“Council voted 6-0 on a resolution that ended a lawsuit from Triboro Commerce Park LLC”
Triboro Commerce Park's seven-data-center plan confirmed withdrawn
“borough engineer Lou LaFratte confirmed the commerce park subsequently withdrew those plans”
Stop Olyphant Data Centers rally at Fern Hill Park
“gathered Sunday afternoon at Fern Hill Park in Olyphant to voice their opposition and share information with the community.”