Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 来源
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 来源
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 来源
| Date | Observed status |
|---|---|
| 2023-10-08 | Land clearing begins simultaneously for all three campuses (west, north, and south) after an [official ceremony](https://web.archive.org/web/20260624112951/http://nmg.news.cn/20231008/57bb95be6791497d |
| 2025-02-24 | On the west zone, building 1 is structurally complete, and building 4 is structurally complete apart from some remaining cooling towers. Buildings 2 and 5 have begun construction. |
| 2025-04-01 | Four buildings are seen to be structurally complete via satellite imagery. |
| 2025-06-01 | On the west zone, building 1 is operational, assuming a 3 month fit out post structural completion, as can be seen via satellite imagery. |
| 2025-07-01 | On the east zone, building 4 is operational, assuming a 3 month fit out post structural completion, as can be seen via satellite imagery. |
| 2026-02-01 | On the west zone, building 2 is operational assuming a 3 month fit out post structural completion, as can be seen via satellite imagery. |
| 2026-03-05 | Three of the six buildings planned across the three campuses (what can be called phase 1) are operational. One other is near completion, apart from backup generators. The third campus does not have co |
| 2026-05-12 | Satellite imagery shows buildings 4 and 5 on the east zone are structurally complete, with landscaping complete. |
| 2026-06-07 | Satellite imagery shows buildings 1 and 2 on the west zone are structurally complete, with landscaping complete. |
| 2026-07-01 | On the east zone, building 5 is operational, assuming a 3 month fit out post structural completion, as can be seen via satellite imagery. |
| 2026-08-18 | On the east zone, building 6 is under construction, and potentially larger than any of the identically sized buildings constructed thus far. Building 3 has not begun construction. |
| 2028-02-14 | Building 6 is operational (estimate). This was the only new building under construction as of August 2026. Buildings in the previous phases each took 1.6 to 2.3 years from laying the foundations to be |
Epoch AI satellite-imagery notes, in date order. · 来源
建设中
Digital infrastructure: AI data-center campus buildout · 核查日期 2026-10-30
仅突出显示已报告的阶段。数据和日期区分规划与已验证状态。
Epoch’s current campus estimate: 184 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 184 MW”
Physical-stage observation dated 2026-08-18. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“building 6 is under construction”
Epoch’s dated 2026-08-18 assessment: building 6 is under construction Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“building 6 is under construction”
Epoch estimates AI hardware: Huawei Ascend 910C chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Huawei Ascend 910C chips.”
Epoch dated observation: Two of the campuses later have the cooling capacity indicative of AI…
“Two of the campuses later have the cooling capacity indicative of AI workloads, while the other (the north campus) does not.”
Epoch dated observation: On the east zone, building 6 is under construction, and potentially…
“On the east zone, building 6 is under construction, and potentially larger than any of the identically sized buildings constructed thus far.”
读者上传的照片,与图钉带来源的媒体分开显示。你可以为吃到或看到的内容评分,在餐厅图钉上还能直接在照片上标记菜品。
第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
保存的日期是估计的跟踪或容量轨迹标记,而不是经过验证的确切开放日期。 施工状况遵循所引用的实际范围; 无法从已完成的目标中推断出完成情况。
Construction research 2026-10-24: Epoch’s[1] 2026-08-18 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “building 6 is under construction” Dated observation 2026-08-18; future trajectory rows and modeled costs are distinguished from this physical milestone.
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
原标题: Huawei Horinger AI Data Center Buildout
位于中国内蒙古呼和浩特市的华为和林格尔是华为运营的前沿人工智能数据中心园区,电力容量达到346.4 MW,拥有168,108个H100等效人工智能加速器。 一份报告表明,在未经证实的第二阶段,Horinger 园区最终可能会增至多达 50 栋建筑。
Epoch 2026 年 8 月 18 日的观察记录了这个命名扩建项目的剩余物理施工/安装情况。 进行中并不完成早期运营的建筑物或未来的容量。 功率和加速器数量仍然是 Epoch 的估计值,而不是运营商认证的评级。 建模的 2025 美元资本成本包括计算硬件,而不是源本地建设预算。