第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
The saved date is an estimated tracking or capacity-trajectory marker, not a verified exact opening day. Construction status follows the cited dated physical scope; no completion is inferred from elapsed targets.
Construction research 2026-10-24: Epoch’s[1] 2026-02-06 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “the building is still clearly a construction zone” Dated observation 2026-02-06; future trajectory rows and modeled costs are distinguished from this physical milestone.
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
Google Red Oak in Red Oak, Texas, United States is a frontier AI data center campus operated by Google reaching 154 MW of power capacity and 279,434 H100-equivalent AI accelerators. Red Oak is unusual for mixing cooling types — one building uses dry coolers while another uses Google’s standard evaporative cooling towers.
Epoch’s 2026-02-06 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget.