Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 来源
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 来源
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 来源
| Date | Observed status |
|---|---|
| 2022-07-01 | Land clearing begins. |
| 2025-05-15 | Building 1 and 2 are operational. Based on Oracle [announcing](https://docs.oracle.com/en-us/iaas/releasenotes/oci/new-region-batam.htm) the Indonesia North (Batam) region is available, and both build |
| 2025-06-13 | Building 3 shell is partly built. Building 1 and 2 look complete. |
| 2025-10-01 | Building 3 has cooling towers beginning to be installed. |
| 2026-03-19 | Building 3 looks complete including building shell, chillers and backup generators. |
| 2026-04-17 | Building 3 is operational. Based on it looking complete as of March, and DayOne [posting](https://www.linkedin.com/posts/dayonedc-datacenter-batam-ugcPost-7450899048925986816-Wxqu/) a video of the fac |
| 2026-05-06 | The three buildings look unchanged since March. |
Epoch AI satellite-imagery notes, in date order. · 来源
商业生产
Digital infrastructure: identified completed AI data-center buildings · 核查日期 2026-10-30
仅突出显示已报告的阶段。数据和日期区分规划与已验证状态。
Epoch’s current campus estimate: 72 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 72 MW”
Physical-stage observation dated 2026-04-17. Named completed buildings only; later expansion is not marked completed. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“fan movement is visible for all buildings”
Epoch’s dated 2026-04-17 assessment: fan movement is visible for all buildings Named completed buildings only; later expansion is not marked completed.
“fan movement is visible for all buildings”
Epoch estimates AI hardware: Nvidia B200 and Nvidia B300 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Nvidia B200 and Nvidia B300 chips.”
Epoch dated observation: Land clearing begins.
“Land clearing begins.”
Epoch dated observation: Building 3 is operational.
“Building 3 is operational.”
Epoch dated observation: The three buildings look unchanged since March.
“The three buildings look unchanged since March.”
读者上传的照片,与图钉带来源的媒体分开显示。你可以为吃到或看到的内容评分,在餐厅图钉上还能直接在照片上标记菜品。
第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
保存的日期是估计的跟踪或容量轨迹标记,而不是经过验证的确切开放日期。 施工状况遵循所引用的实际范围; 无法从已完成的目标中推断出完成情况。
Construction research 2026-10-24: Epoch’s[1] 2026-04-17 observation documents the identified building scope complete or operating, using physical observations or explicit delivery rather than an elapsed target date. Completed is limited to that scope. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “fan movement is visible for all buildings” Dated observation 2026-04-17; future trajectory rows and modeled costs are distinguished from this physical milestone.
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
原标题: Oracle Batam AI Data Center — Completed Buildings
位于印度尼西亚廖内群岛巴淡岛的 Oracle Batam 是由 Oracle / 腾讯运营的前沿 AI 数据中心园区,电力容量达到 72 MW,拥有 84,386 个 H100 等效 AI 加速器。 0
Epoch 的 2026 年 4 月 17 日观察记录了已确定的建筑范围已完成或正在运行,使用物理观察或明确交付而不是已过的目标日期。 完成的仅限于该范围。 功率和加速器数量仍然是 Epoch 的估计值,而不是运营商认证的评级。 建模的 2025 美元资本成本包括计算硬件,而不是源本地建设预算。