第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
开始是Epoch[3][7]卫星观测的土地清理工作;Crusoe 表示,施工将于 2024 年 6 月开始。Epoch 预计 7-8 号楼的运营将于 2026 年 11 月结束;没有公布开发者日期。
Cited in the project timeline.[1]
Construction research 2026-10-24: Epoch’s[1][7] 2026-07-28 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “not yet confirmed operational” Dated observation 2026-07-28; future trajectory rows and modeled costs are distinguished from this physical milestone.
Cited in the project timeline.[1]
| 2025-06-28 | 1 号楼看起来已接近竣工,冷却装置已就位。OpenAI [声明](https://openai.com/index/ Five-new-stargate-sites/)“Oracle 开始交付第一批 NVIDIA GB200 机架 |
|---|
| 2025-09-26 | 1 号楼于该日期前后全面投入使用。根据 Crusoe [公告],第一阶段已于 9 月 30 日“上线”(https://www.crusoe.ai/resources/newsroom/crusoe-announces-flagship-abilen |
|---|
| 2025-12-24 | 2号楼已全面投入使用。根据 [TDLR 文件](https:// |
|---|
| 2026-01-15 | 1 GW 变电站看起来即将完工。3 号楼似乎已安装所有电力和冷却设备,但仍有施工迹象。这似乎是我的行动的正轨 |
|---|
| 2026-03-24 | 3号楼和4号楼看起来已经完工,但尚未完全投入使用。旁边停着的汽车数量没有 1-2 号楼那么多,这表明汽车可能仍在增加。根据 4 号楼目前已到期 |
|---|
| 2026-05-23 | 3号楼和4号楼预计投入使用。4 月 22 日,Oracle [发布](https://x.com/i/status/2047012589302153558) 表示“在阿比林,200MW 已经投入运营”。这表明有 |
|---|
| 2026-07-28 | 5-8号楼结构完整,有屋顶,但尚未确认投入使用(装修正在进行中)。变电站看起来已经完成。 |
|---|
| 2026-09-10 | 5-6号楼投入使用。在 Oracle 2027 财年第一季度财报电话会议上(2026 年 9 月 10 日),Clay Magouyrk 表示:“8 座园区建筑中的 6 座(代表 618 兆瓦和总容量的 75%)现已 |
|---|
| 2026-11-01 | 7-8 号楼预计投入使用。3月24日,8号楼的样子与9月份的3号楼大致相同。3号楼预计将于7个月后的4月份投入使用。这个n |
|---|
Epoch AI 卫星图像注释,按日期顺序排列。 · 来源
About 4 million sq ft, eight buildings
“bringing the campus to eight buildings, about 4 million square feet and 1.2 gigawatts”
875 acres
“sits Stargate — an 875-acre AI data center campus”
618 MW delivered of 824 MW IT projected (Epoch); campus 1.2 GW grid-level design
“said six of the eight buildings, representing 618 megawatts and 75 percent of the campus, had been delivered”
Six of eight buildings delivered; Buildings 7-8 fit-out
“Buildings 5-6 are operational.”
Land clearing begins for Buildings 1-2 (Epoch satellite observation)
“Land clearing begins for northern two buildings (Building 1-2)”
City council approves 85%, 10-year tax abatements
“The Abilene City Council approved 85 percent, 10-year property tax abatements for the site in February 2025”
Second phase of six more buildings announced (eight total, 1.2 GW)
“announced a second phase of six more buildings, bringing the campus to eight buildings, about 4 million square feet and 1.2 gigawatts”
$15 billion Crusoe/Blue Owl/Primary Digital joint venture announced for the campus
“On May 21, 2025, Crusoe, Blue Owl Capital and Primary Digital Infrastructure announced the second phase of a $15 billion joint venture to fund the campus.”
Buildings 1-2 live on Oracle Cloud Infrastructure
“Crusoe said on Sept. 30, 2025, that the first phase was running on Oracle Cloud Infrastructure”
Crusoe tops out the eighth and final building
“Crusoe has marked a major milestone in its AI infrastructure expansion by topping out the eighth and final building”
Building 2 fully operational (Epoch estimate; matches TDLR completion date)
“Building 2 is fully operational.”
OpenAI and Oracle drop plan to expand Abilene beyond about 1.2 GW
“OpenAI had planned to expand this site to 2.1 GW, but recently reversed course”
Buildings 5-8 structurally complete and roofed; fit-out ongoing
“Buildings 5-8 are structurally complete and roofed but not yet confirmed operational (fit-out ongoing).”
Oracle: six of eight buildings, 618 MW, delivered
“said six of the eight buildings, representing 618 megawatts and 75 percent of the campus, had been delivered”
Buildings 7-8 estimated operational (full campus; Oracle gave no date)
“Buildings 7-8 are estimated to be operational.”
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
原标题: OpenAI Stargate Abilene AI Data Center Buildout
OpenAI 位于德克萨斯州阿比林的 Stargate 园区是 Crusoe 租给 Oracle 的八栋建筑,面积约 400 万平方英尺,容量为 1.2 GW。2024年开始建设;Oracle 报告称,八栋建筑中有六栋已于 2026 年 9 月 10 日交付,最后两栋仍在装修。一家价值 150 亿美元的合资企业为该园区提供资金。Epoch AI 估计 IT 电力目前为 618 MW,完工后为 824 MW。
Epoch 2026 年 7 月 28 日的观察记录了这个命名扩建项目的剩余物理施工/安装情况。 进行中并不完成早期运营的建筑物或未来的容量。 功率和加速器数量仍然是 Epoch 的估计值,而不是运营商认证的评级。 建模的 2025 美元资本成本包括计算硬件,而不是源本地建设预算。
Epoch AI 通过带注释的卫星足迹(70 个物理部件)跟踪超大规模前沿 AI 训练和推理园区。