Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 来源
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 来源
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 来源
| Date | Observed status |
|---|---|
| 2024-03-01 | Land clearing begins. |
| 2025-07-04 | Building 1 and 2 under construction, with all chillers visible. |
| 2026-03-20 | Buildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site and few cars in the front carpark, so we expect 3 more months needed for commissioning and server install |
| 2026-06-18 | We estimate Buildings 1 and 2 are operational. |
| 2027-02-02 | Buildings 5 and 6 are operational (estimate). Based on the tent buildings at Meta Prometheus taking about 12 months from starting the tent structure to estimated operation. |
| 2027-02-23 | Buildings 3 and 4 are operational (estimate). In September 2025, Building 1 and 2 appeared to be in a similar state to Building 3 and 4 in May 2026. Based on that, we apply an 8-month delay to the Bui |
Epoch AI satellite-imagery notes, in date order. · 来源
建设中
Digital infrastructure: AI data-center campus buildout · 核查日期 2026-10-30
仅突出显示已报告的阶段。数据和日期区分规划与已验证状态。
Epoch’s current campus estimate: 153 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 153 MW”
Physical-stage observation dated 2026-03-20. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Buildings 5 and 6 are under construction.”
Epoch’s dated 2026-03-20 assessment: Buildings 5 and 6 are under construction. Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Buildings 5 and 6 are under construction.”
Epoch estimates AI hardware: Nvidia B300 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Nvidia B300 chips.”
Epoch dated observation: Land clearing begins.
“Land clearing begins.”
Epoch assessment: Buildings 1 and 2 are nearly complete, but there's still some equipment…
“Buildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site and few cars in the front carpark, so we expect 3 more months needed for commissioning and server installation.”
Epoch assessment: We estimate Buildings 1 and 2 are operational.
“We estimate Buildings 1 and 2 are operational.”
读者上传的照片,与图钉带来源的媒体分开显示。你可以为吃到或看到的内容评分,在餐厅图钉上还能直接在照片上标记菜品。
第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
保存的日期是估计的跟踪或容量轨迹标记,而不是经过验证的确切开放日期。 施工状况遵循所引用的实际范围; 无法从已完成的目标中推断出完成情况。
Construction research 2026-10-24: Epoch’s[1] 2026-03-20 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Buildings 5 and 6 are under construction.” Dated observation 2026-03-20; future trajectory rows and modeled costs are distinguished from this physical milestone.
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
原标题: Meta Montgomery AI Data Center Buildout
Epoch 的 2026 年 3 月 20 日观察记录了该指定扩建项目的剩余物理施工/安装情况。 进行中并不完成早期运营的建筑物或未来的容量。 功率和加速器数量仍然是 Epoch 的估计值,而不是运营商认证的评级。 建模的 2025 美元资本成本包括计算硬件,而不是源本地建设预算。
Epoch AI 通过带注释的卫星足迹(18 个物理部分)跟踪超大规模前沿 AI 训练和推理园区。