Epoch[3] 的土地清理工作开始于卫星日期(2024 年 5 月 30 日);政府发布的消息称将于 2027 年春季投入运营(季节精度),因此 endDate 为空。
Cited in the project timeline.[1]
Construction research 2026-10-24: Epoch’s[1] 2026-04-08 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “there's still some equipment strewn around the site” Dated observation 2026-04-08; future trajectory rows and modeled costs are distinguished from this physical milestone.
Cited in the project timeline.[1]
Cited in the project timeline.[1]
| 2026-04-08 | 1 号楼和 2 号楼已接近完工,但现场仍散落着一些设备。我们预计调试和服务器安装还需要大约 3 个月的时间。 |
|---|
| 2026-08-07 | 通过无人机图像确认 1 号楼可运行,其中有 8/9 组带有旋转风扇的冷却器。图像还确认 2 号楼的所有冷却和电力基础设施均已到位。 |
|---|
| 2026-11-05 | 假设与 1 号楼相比,2 号楼的运营晚了 3 个月。 |
|---|
Epoch AI 卫星图像注释,按日期顺序排列。 · 来源
100 operational jobs and 1,000 construction jobs
“will bring 100 operational jobs as well as 1,000 construction jobs”
715,000 sq ft
“the 715,000-square-foot data center, located in the Sage Mill Industrial Park in Aiken County”
300+ acres
“Situated on a 300+ acre site in Aiken County, South Carolina”
69 MW now; 129 MW projected
“supported by 69 MW of IT power”
Building 1 operational; Building 2 commissioning
“Building 1 is confirmed operational via drone imagery with 8/9 group of coolers with spinning fans.”
Land clearing begins (satellite)
“Land clearing begins”
Meta announces $800 million Aiken County data center
“The $800 million investment will support 100 new operational jobs.”
SELC files FOIA request on projected water use and incentives
“the Southern Environmental Law Center requested documents from Aiken County regarding the anticipated water usage of Meta's proposed data center”
Data center under construction at Sage Mill
“Meta is building one of the massive information storage facilities at the Sage Mill Industrial Park in the Graniteville/Vaucluse area.”
Buildings 1 and 2 nearly complete (satellite)
“Buildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site.”
Building 1 confirmed operational via drone imagery
“Building 1 is confirmed operational via drone imagery with 8/9 group of coolers with spinning fans.”
Building 2 operational (Epoch projection)
“Building 2 is operational assuming a 3 month lag compared to Building 1.”
Meta's operational target for the data center
“It is expected to be operational in spring 2027.”
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
原标题: Meta Aiken AI Data Center Buildout
Meta 的第一个南卡罗来纳州数据中心是一个耗资 8 亿美元、占地 715,000 平方英尺的人工智能优化园区,位于艾肯县 Graniteville 附近的 Sage Mill 工业园区。土地清理工作于 2024 年 5 月开始,Epoch 的无人机审查确认 1 号楼已于 2026 年 8 月投入运营,2 号楼仍在调试中,Meta 的园区目标是 2027 年春季。
Epoch 2026 年 4 月 8 日的观察记录了这个指定扩建项目的剩余物理施工/安装情况。进行中并不完成早期运营的建筑物或未来的容量。功率和加速器数量仍然是 Epoch 的估计值,而不是运营商认证的评级。建模的 2025 美元资本成本包括计算硬件,而不是源本地建设预算。
Epoch AI 通过带注释的卫星足迹(6 个物理部分)跟踪超大规模前沿 AI 训练和推理园区。